9001 S BARING CROSS ST 90044

Certificate Information: 9001 S BARING CROSS ST 90044

Application / Permit
24010-10000-01568
Plan Check / Job No.
B24LA06966
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: NEW 2-STORY DUPLEX W/ ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 YASHAR EMAMI
Corrections Issued 5/9/2024 YASHAR EMAMI
Quality Review Completed 5/24/2024 KAVIAN REFAHI
Applicant returned to address corrections 2/13/2025 YASHAR EMAMI
Applicant returned to address corrections 2/27/2025 YASHAR EMAMI
Applicant returned to address corrections 3/5/2025 YASHAR EMAMI
Plan Check Approved 3/19/2025 YASHAR EMAMI
Issued 3/25/2025 APPLICANT
CofO in Progress 10/15/2025 JOHN QUINTANILLA
Permit Finaled 10/17/2025 DEROLD HAUFF
CofO Issued 10/17/2025 DEROLD HAUFF
Permit Finaled 10/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/15/2024 SARAH YOUSSEF
Address approval Cleared 6/18/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 6/18/2024 JUSTIN BICOL
Trees in Parkway Cleared 7/8/2024 ADALBERTO VERA
Permit Cleared 7/16/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 8/12/2024 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 1/29/2025 TREVOR QUAN
Sewer availability Cleared 1/29/2025 TREVOR QUAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 5/15/2025 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval JOHN QUINTANILLA
Insulation 5/16/2025 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 7/14/2025 Approved JOHN QUINTANILLA
HVAC-Rough 7/14/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 7/15/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 7/15/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 7/15/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 7/17/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 7/17/2025 Approved JOHN QUINTANILLA
Insulation 7/18/2025 Approved RONNIE MEDINA
Drywall Nailing 8/15/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 8/15/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 9/26/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 9/26/2025 Corrections Issued SALVADOR MARTINEZ
Final 9/29/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 9/29/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 9/29/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 9/29/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 9/29/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 9/30/2025 Approved JOHN QUINTANILLA
HVAC-Final 9/30/2025 Approved JOHN QUINTANILLA
Special/Order Compliance 10/2/2025 Conditional Approval JOHN QUINTANILLA
Final 10/8/2025 OK to Issue CofO JOHN QUINTANILLA
Service/Power Release 10/8/2025 Approved JOHN QUINTANILLA