16782 W OTSEGO ST 91436

Certificate Information: 16782 W OTSEGO ST 91436

Application / Permit
24010-10000-01566
Plan Check / Job No.
B24LA06949
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTAHCED GARAGE (2-STORY)
Permit Issued
Issued on 9/7/2024
Issuing Office
Current Status
CofO in Progress on 4/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 4/25/2024 CARLOS MONTES
Corrections Issued 4/29/2024 CARLOS MONTES
Quality Review Completed 5/2/2024 GARO TELMI
Plan Check Approved 9/3/2024 CARLOS MONTES
Issued 9/7/2024 APPLICANT
CofO in Progress 4/3/2026 THOMAS FINNILA

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/10/2024 SARAH YOUSSEF
Address approval Cleared 6/4/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/4/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/5/2024 BIAINA HARITUNIAN
Trees in Parkway Cleared 6/7/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 6/16/2024 JOHN CONNEALLY
Permit Cleared 6/17/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 11/25/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/25/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 11/25/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 12/5/2024 Approved JOHN COLEMAN
Deputy Drilled-In Anchors 12/30/2024 Partial Approval SEAN WIRCH
Deputy Wood Construction 12/30/2024 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Partial Approval THOMAS FINNILA
Structural Steel Frame 1/3/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval THOMAS FINNILA
Deputy Wood Construction 1/16/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 2/6/2025 Approved JEFFREY HARTLINE
Deputy Wood Construction 2/10/2025 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 2/14/2025 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 2/14/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 2/20/2025 Corrections Issued THOMAS FINNILA
HVAC-Rough 2/20/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 2/25/2025 Approved JOHN COLEMAN
ELECTRICAL-Rough 3/3/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 3/10/2025 Corrections Issued THOMAS FINNILA
Green Building Rough 3/10/2025 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 3/10/2025 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/25/2025 Approved MORRIS JACKSON
Green Building Rough 3/25/2025 Approved MORRIS JACKSON
Insulation 3/25/2025 Approved MORRIS JACKSON
MERV13>=Rough 3/25/2025 Approved MORRIS JACKSON
Drywall Nailing 4/1/2025 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 4/1/2025 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 4/7/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/7/2025 Partial Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 6/11/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 10/1/2025 Approved MORRIS JACKSON
HVAC-Final 11/17/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 11/17/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 11/20/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 11/20/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 12/4/2025 Approved THOMAS FINNILA
Final 12/4/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 12/4/2025 Approved THOMAS FINNILA
HVAC-Final 12/4/2025 Approved THOMAS FINNILA
HVAC-Final 3/5/2026 Approved THOMAS FINNILA
Service/Power Release 3/17/2026 Corrections Issued THOMAS FINNILA
Service/Power Release 4/1/2026 Approved THOMAS FINNILA
Final 4/2/2026 OK to Issue CofO THOMAS FINNILA
Green Building Final 4/2/2026 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved THOMAS FINNILA
Smoke Detectors 4/2/2026 Approved THOMAS FINNILA