2657-2657 1/2 S DALTON AVE 90018
Certificate Information: 2657-2657 1/2 S DALTON AVE 90018
- Application / Permit
- 24010-10000-01564
- Plan Check / Job No.
- B24LA06939
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 4 stories duplex.
- Permit Issued
- Issued on 10/8/2024
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | JOE VO |
| Corrections Issued | 4/28/2024 | JOE VO |
| Quality Review Completed | 4/30/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/29/2024 | JOE VO |
| Plan Check Approved | 10/1/2024 | JOE VO |
| Issued | 10/8/2024 | APPLICANT |
| CofO in Progress | 2/13/2026 | WILLIAM SIERRA |
| No Progress | 2/15/2026 | DEROLD HAUFF |
| CofO in Progress | 2/15/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2024 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 6/17/2024 | SARAH YOUSSEF |
| Community Plan Implem. Overlay | Cleared | 6/26/2024 | MANERI ROMAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 7/5/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 7/11/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 7/19/2024 | JOHN CONNEALLY |
| Permit | Cleared | 9/4/2024 | CELINA MORENO |
| Highway dedication | Cleared | 9/13/2024 | CELINA MORENO |
| Building over 36-ft | Cleared | 9/16/2024 | CALOSHA APPROVED |
Contact Information
| Contractor | Tre Development Llc; Lic. No.: 1075573-B | , |
| Engineer | Xia,, Ji; Lic. No.: S7144 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 3/7/2025 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 3/11/2025 | Approved | WILLIAM SIERRA |
| Sewer | 3/12/2025 | Approved | WILLIAM SIERRA |
| Deputy Reinf. Concrete | 3/20/2025 | Conditional Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Approved | WILLIAM SIERRA |
| Footing/Foundation/Slab | 3/21/2025 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 3/21/2025 | Approved | WILLIAM SIERRA |
| Deputy Reinf. Concrete | 3/25/2025 | Conditional Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | WILLIAM SIERRA |
| Deputy Wood Construction | 4/28/2025 | Conditional Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Partial Approval | WILLIAM SIERRA |
| Deputy Wood Construction | 6/25/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Rough | 7/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Rough | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 7/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Rough | 7/10/2025 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 7/15/2025 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 7/31/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 8/7/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 8/7/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 8/7/2025 | Conditional Approval | WILLIAM SIERRA |
| Special/Order Compliance | 8/7/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 8/8/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 8/8/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 8/8/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 8/12/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 8/12/2025 | Approved | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 8/13/2025 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 8/27/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 9/8/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 9/22/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 10/14/2025 | No Access for Inspection | ALEX COLIN |
| Underground Mechanical | 10/17/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 10/24/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 11/12/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 11/12/2025 | Corrections Issued | WILLIAM SIERRA |
| Smoke Detectors | 11/12/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 11/18/2025 | No Access for Inspection | WILLIAM SIERRA |
| HVAC-Final | 11/20/2025 | Approved | WILLIAM SIERRA |
| Special/Order Compliance | 12/17/2025 | Partial Inspection | WILLIAM SIERRA |
| Final | 1/23/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 1/23/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 1/23/2026 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | WILLIAM SIERRA |
| Service/Power Release | 1/23/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 1/30/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 1/30/2026 | Approved | WILLIAM SIERRA |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 2/5/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Service/Power Release | 2/5/2026 | Approved | WILLIAM SIERRA |
| Final | 2/13/2026 | OK to Issue CofO | WILLIAM SIERRA |