6713 W DREXEL AVE 90048
Certificate Information: 6713 W DREXEL AVE 90048
- Application / Permit
- 24010-10000-01535
- Plan Check / Job No.
- B24LA06836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW TWO STORY DETACHED ADU. DETACHED ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g).
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | ADRIANA LOPEZ |
| Corrections Issued | 5/2/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 5/21/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 10/7/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 10/8/2024 | ADRIANA LOPEZ |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 8/27/2025 | EVAN COOPER |
| Permit Finaled | 9/18/2025 | RICHARD STEINBACH |
| CofO Issued | 9/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 6/21/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 9/4/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/4/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/15/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/18/2024 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 12/5/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 12/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 12/5/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 12/11/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 12/11/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 12/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/19/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/23/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2025 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/22/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/24/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 2/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 2/27/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 3/4/2025 | Approved | ARAM AVEDISIAN |
| METHANE-Rough | 3/4/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/7/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/7/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/14/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/17/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Sewer | 4/14/2025 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 4/21/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 4/23/2025 | Conditional Approval | EVAN COOPER |
| Service/Power Release | 5/13/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 7/30/2025 | Approved | EVAN COOPER |
| Final | 7/30/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 7/30/2025 | Approved | EVAN COOPER |
| HVAC-Final | 7/30/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 7/30/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 7/30/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/27/2025 | Approved | EVAN COOPER |
| Final | 8/27/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 8/27/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/27/2025 | Approved | EVAN COOPER |