3206 1/2 W 18TH ST 90019
Certificate Information: 3206 1/2 W 18TH ST 90019
- Application / Permit
- 24010-10000-01497
- Plan Check / Job No.
- B24LA06720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. NEW DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2024 | FERNANDO FLORES |
| Corrections Issued | 4/17/2024 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/23/2024 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/11/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 12/17/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 12/23/2024 | ALEXANDER JOO |
| Plan Check Approved | 1/9/2025 | ALEXANDER JOO |
| Issued | 1/16/2025 | APPLICANT |
| CofO in Progress | 8/15/2025 | WILLIAM SIERRA |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
| CofO Issued | 8/21/2025 | DEROLD HAUFF |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/2/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | WALLIE JONG |
| Sewer availability | Cleared | 5/13/2024 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 6/24/2024 | HUGO GARRIDO GARZA |
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 1/8/2025 | ISAIAH ROSS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2025 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 2/28/2025 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 2/28/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 3/11/2025 | Partial Approval | WILLIAM SIERRA |
| Sewer | 3/11/2025 | Approved | WILLIAM SIERRA |
| Insulation | 3/19/2025 | Partial Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 4/3/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/10/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 4/10/2025 | Conditional Approval | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/25/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 4/25/2025 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Rough | 4/25/2025 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 4/25/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 5/2/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/2/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 5/2/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 5/6/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/6/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 5/6/2025 | Approved | WILLIAM SIERRA |
| Shower Pan | 5/6/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 5/6/2025 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 6/2/2025 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Service/Power Release | 7/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 7/2/2025 | Approved | WILLIAM SIERRA |
| Final | 7/18/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 7/18/2025 | Corrections Issued | WILLIAM SIERRA |
| Service/Power Release | 7/18/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 7/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 7/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Service/Power Release | 7/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 7/29/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Final | 7/29/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 7/29/2025 | Approved | ARTHUR NEGRETE |
| Final | 8/15/2025 | OK to Issue CofO | WILLIAM SIERRA |