Issued on 1/16/2025
Issuing Office
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/17/2024 FERNANDO FLORES
Corrections Issued 4/17/2024 FERNANDO FLORES
Applicant returned to address corrections 7/23/2024 FERNANDO FLORES
Applicant returned to address corrections 9/11/2024 CARLOS MONTES
Applicant returned to address corrections 12/17/2024 ALEXANDER JOO
Applicant returned to address corrections 12/23/2024 ALEXANDER JOO
Plan Check Approved 1/9/2025 ALEXANDER JOO
Issued 1/16/2025 APPLICANT
CofO in Progress 8/15/2025 WILLIAM SIERRA
Permit Finaled 8/21/2025 DEROLD HAUFF
CofO Issued 8/21/2025 DEROLD HAUFF
Permit Finaled 8/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/2/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 5/2/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/13/2024 WALLIE JONG
Sewer availability Cleared 5/13/2024 WALLIE JONG
Tenant Habitability Plan Cleared 6/24/2024 HUGO GARRIDO GARZA
Construction near power lines Cleared 10/7/2024 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 1/8/2025 ISAIAH ROSS

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/28/2025 Approved WILLIAM SIERRA
METHANE-Barrier 2/28/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 2/28/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 3/11/2025 Partial Approval WILLIAM SIERRA
Sewer 3/11/2025 Approved WILLIAM SIERRA
Insulation 3/19/2025 Partial Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 4/3/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 4/10/2025 Approved WILLIAM SIERRA
HVAC-Rough 4/10/2025 Conditional Approval WILLIAM SIERRA
BUILDING-Rough-Frame 4/25/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved WILLIAM SIERRA
Green Building Rough 4/25/2025 Corrections Issued WILLIAM SIERRA
METHANE-Rough 4/25/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 4/25/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 5/2/2025 Approved WILLIAM SIERRA
Green Building Rough 5/2/2025 Approved WILLIAM SIERRA
Insulation 5/2/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 5/2/2025 Approved WILLIAM SIERRA
Drywall Nailing 5/6/2025 Approved WILLIAM SIERRA
Insulation 5/6/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 5/6/2025 Approved WILLIAM SIERRA
Shower Pan 5/6/2025 Approved WILLIAM SIERRA
Wood Frame 5/6/2025 Approved WILLIAM SIERRA
Underground Mechanical 6/2/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Final 7/2/2025 Corrections Issued WILLIAM SIERRA
Final 7/2/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 7/2/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 7/2/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 7/2/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 7/2/2025 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 7/2/2025 Approved WILLIAM SIERRA
Final 7/18/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 7/18/2025 Corrections Issued WILLIAM SIERRA
Service/Power Release 7/18/2025 Not Ready for Inspection WILLIAM SIERRA
Final 7/25/2025 Not Ready for Inspection RONNIE MINDANAO
Green Building Final 7/25/2025 Not Ready for Inspection RONNIE MINDANAO
Service/Power Release 7/25/2025 Not Ready for Inspection RONNIE MINDANAO
Final 7/29/2025 Conditional Approval ARTHUR NEGRETE
Green Building Final 7/29/2025 Approved ARTHUR NEGRETE
Service/Power Release 7/29/2025 Approved ARTHUR NEGRETE
Final 8/15/2025 OK to Issue CofO WILLIAM SIERRA