7105 N YARMOUTH AVE 91335
Certificate Information: 7105 N YARMOUTH AVE 91335
- Application / Permit
- 24010-10000-01478
- Plan Check / Job No.
- B24LA06637
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW DET. ADU PER CA Govt. Code 65852.2(e)(1)(D) and applicable partof LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Current Status
- CofO Issued on 5/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/1/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/1/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/15/2024 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 8/8/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/11/2024 | MAHNAZ NOURHASHEMI |
| Issued | 9/19/2024 | APPLICANT |
| CofO in Progress | 4/22/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 5/21/2025 | JOHN JANSON |
| CofO Issued | 5/21/2025 | JOHN JANSON |
| Permit Finaled | 5/21/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 5/4/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 5/6/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2024 | TAL SHEMEN |
| Senate Bill 9 | Cleared | 7/2/2024 | BRENNEN OBETO |
| Construction near power lines | Cleared | 8/9/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/7/2024 | Corrections Issued | JEFFREY BULL |
| Underground Mechanical | 10/7/2024 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Corrections Issued | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 12/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/16/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 12/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/24/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/24/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 12/24/2024 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/24/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 12/24/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/30/2024 | Partial Inspection | JOHN COLEMAN |
| Green Building Rough | 12/30/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 12/30/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/2/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 1/2/2025 | Approved | MORRIS JACKSON |
| Insulation | 1/2/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 1/7/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/3/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/3/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 3/3/2025 | Not Required | ARUTYUN MADATYAN |
| Smoke Detectors | 3/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/7/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Service/Power Release | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/22/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/22/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 4/22/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/22/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/22/2025 | Approved | ARUTYUN MADATYAN |