9150 S FALMOUTH AVE 90293

Certificate Information: 9150 S FALMOUTH AVE 90293

Application / Permit
24010-10000-01440
Plan Check / Job No.
B24LA06426
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
**ePlan**LAX** NEW (2) STORY FITNESS FACILITIES, LOCKER ROOMS, OFFICES, & RETRACTABLE CANOPY VIEWING PLATFORM
Permit Issued
Issued on 6/5/2025
Issuing Office
Current Status
Issued on 6/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/10/2024 APPLICANT
Assigned to Plan Check Engineer 4/10/2024 FARSHAD ALIMOHAMADI
Corrections Issued 4/15/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 4/16/2024 LIPING TENG
Applicant returned to address corrections 7/26/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/14/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/29/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/2/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/28/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 5/30/2025 FARSHAD ALIMOHAMADI
Issued 6/5/2025 APPLICANT

Permit Application Clearance Information

Permit Cleared 4/25/2024 KATHLEEN LEE
Address approval Cleared 5/23/2024 ANTHONY MAINEZ
Highway dedication Cleared 7/2/2024 VLADIMIR ARUTYUNYAN
City owned building/parcel Cleared 7/18/2024 FARSHAD ALIMOHAMADI
GPI Written Notices Cleared 10/29/2024 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 10/29/2024 FARSHAD ALIMOHAMADI
Trees in Parkway Cleared 1/13/2025 ADALBERTO VERA
Sewer availability Cleared 4/29/2025 HISASHI KOBAYAKAWA
Project Permit Cleared 5/5/2025 CHRISTOPHER MARTINEZ
Specific Plan Cleared 5/5/2025 CAELAN RAFFERTY
Low Impact Development (LID) Cleared 5/11/2025 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 5/16/2025 HISASHI KOBAYAKAWA
Driveway location Cleared 5/17/2025 EDUARDO HERMOSO
Internal circulation Cleared 5/17/2025 EDUARDO HERMOSO
Roof/Waste drainage to street Cleared 5/21/2025 KIMBERLY HERNANDEZ
Fire Marshal Fire Life Safety Cleared 5/22/2025 MENOA AGHAJANI
Hydrant and Access approval Cleared 5/22/2025 JOHN CONNEALLY
Specific Plan Cleared 5/25/2025 EDUARDO HERMOSO

Contact Information

Contractor Dpr Construction A General Partnership; Lic. No.: 1083716-B P O BOX 5614      REDWOOD CITY, CA 94063

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2025 Partial Approval NICK LAROCCA
METHANE-Rough 12/4/2025 Not Ready for Inspection NICK LAROCCA
Reinforced Masonry Frame 12/4/2025 Partial Approval NICK LAROCCA
Verify Sprinkler Sign Off 12/4/2025 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 12/8/2025 Partial Approval NICK LAROCCA
METHANE-Rough 12/19/2025 Approved NICK LAROCCA
Reinforced Masonry Frame 12/19/2025 Partial Approval NICK LAROCCA
Reinforced Masonry Frame 1/14/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 1/15/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/20/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/21/2026 Approved NICK LAROCCA
Reinforced Masonry Frame 1/22/2026 Partial Approval RICARDO ROBLES
Deputy Reinf. Masonry 2/5/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/9/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/11/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/11/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 2/11/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 2/12/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/13/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/13/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/25/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 2/25/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 3/2/2026 Approved NICK LAROCCA
Deputy Drilled-In Anchors 3/3/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/3/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/18/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/18/2026 Approved NICK LAROCCA
Deputy Steel/Welding 3/31/2026 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 5/4/2026 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 6/29/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/30/2026 Approved NICK LAROCCA
Deputy Reinf. Masonry 7/7/2026 Conditional Approval DAVID TSAU
Deputy Wood Construction 7/7/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/14/2026 Approved NICK LAROCCA
Deputy Steel/Welding 7/14/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/20/2026 Approved NICK LAROCCA
Deputy Reinf. Concrete 7/21/2026 Approved NICK LAROCCA