4228 S EAST BLVD 90066
Certificate Information: 4228 S EAST BLVD 90066
- Application / Permit
- 24010-10000-01422
- Plan Check / Job No.
- B24LA05094
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) (1-STORY)
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | CARLOS MONTES |
| Corrections Issued | 4/9/2024 | CARLOS MONTES |
| Quality Review Completed | 4/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/8/2024 | CARLOS MONTES |
| Plan Check Approved | 11/21/2024 | CARLOS MONTES |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 12/16/2025 | WILBER ROSALES |
| CofO in Progress | 12/29/2025 | DAVID FEILER |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/22/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 4/26/2024 | DINAH GARIN |
| Specific Plan | Cleared | 5/30/2024 | RICHARD WOO |
| Hydrant and Access approval | Cleared | 5/31/2024 | GILBERT URREA |
| Miscellaneous | Cleared | 7/9/2024 | DARIN LAM |
| ZA Case | Cleared | 7/16/2024 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | DINAH GARIN |
| Sewer availability | Cleared | 7/24/2024 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 11/21/2024 | CALOSHA APPROVED |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/19/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/19/2025 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 2/19/2025 | Partial Approval | BOBBY KEY |
| Deputy Pre-Stress Concrete | 3/4/2025 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 3/4/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 3/7/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 3/7/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/23/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/23/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/28/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 5/2/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | BOBBY KEY |
| Green Building Rough | 6/3/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/3/2025 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/3/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/3/2025 | Corrections Issued | BOBBY KEY |
| Verify Sprinkler Sign Off | 6/3/2025 | Approved | BOBBY KEY |
| Insulation | 6/16/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 6/24/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 7/2/2025 | Partial Approval | JAYLIN GRAVITTE |
| Shower Pan | 7/25/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 9/8/2025 | Conditional Approval | MICHAEL ALLEN |
| Smoke Detectors | 9/8/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 9/16/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 10/16/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 10/16/2025 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Final | 10/24/2025 | Approved | WILBER ROSALES |
| Final | 11/13/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 11/13/2025 | Conditional Approval | WILBER ROSALES |
| HVAC-Final | 11/13/2025 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Not Required | WILBER ROSALES |
| Final | 12/10/2025 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 12/10/2025 | Not Ready for Inspection | WILBER ROSALES |
| Service/Power Release | 12/10/2025 | Partial Inspection | WILBER ROSALES |
| Final | 12/15/2025 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 12/15/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 12/15/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 12/15/2025 | Approved | WILBER ROSALES |