4228 S EAST BLVD 90066

Certificate Information: 4228 S EAST BLVD 90066

Application / Permit
24010-10000-01422
Plan Check / Job No.
B24LA05094
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) (1-STORY)
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 CARLOS MONTES
Corrections Issued 4/9/2024 CARLOS MONTES
Quality Review Completed 4/9/2024 GARO TELMI
Applicant returned to address corrections 8/8/2024 CARLOS MONTES
Plan Check Approved 11/21/2024 CARLOS MONTES
Issued 11/21/2024 APPLICANT
CofO in Progress 12/16/2025 WILBER ROSALES
CofO in Progress 12/29/2025 DAVID FEILER
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/22/2024 SARAH YOUSSEF
Address approval Cleared 4/26/2024 DINAH GARIN
Specific Plan Cleared 5/30/2024 RICHARD WOO
Hydrant and Access approval Cleared 5/31/2024 GILBERT URREA
Miscellaneous Cleared 7/9/2024 DARIN LAM
ZA Case Cleared 7/16/2024 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 7/24/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 7/24/2024 DINAH GARIN
Sewer availability Cleared 7/24/2024 DINAH GARIN
Excavation more than 5-ft deep Cleared 11/21/2024 CALOSHA APPROVED

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: NA23971       ,
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B       ,
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nguyen,, Huan; Lic. No.: NA64238       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/19/2025 Approved BOBBY KEY
Special/Order Compliance 2/19/2025 Corrections Issued BOBBY KEY
Underground Mechanical 2/19/2025 Partial Approval BOBBY KEY
Deputy Pre-Stress Concrete 3/4/2025 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 3/4/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 3/7/2025 Approved MICHAEL ALLEN
Special/Order Compliance 3/7/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Wood Construction 3/28/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 4/23/2025 Approved MICHAEL ALLEN
HVAC-Rough 4/23/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 4/28/2025 Approved TEMISTOCLES CAAL
Underground Mechanical 5/2/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 6/3/2025 Approved BOBBY KEY
Green Building Rough 6/3/2025 Approved BOBBY KEY
Interior/Exterior Lathing 6/3/2025 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 6/3/2025 Approved BOBBY KEY
Special/Order Compliance 6/3/2025 Corrections Issued BOBBY KEY
Verify Sprinkler Sign Off 6/3/2025 Approved BOBBY KEY
Insulation 6/16/2025 Approved RUBEN RIVAS
Drywall Nailing 6/24/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 7/2/2025 Partial Approval JAYLIN GRAVITTE
Shower Pan 7/25/2025 Approved WILBER ROSALES
ELECTRICAL-Final 9/8/2025 Conditional Approval MICHAEL ALLEN
Smoke Detectors 9/8/2025 Approved MICHAEL ALLEN
PLUMBING-Final 9/16/2025 Approved WILBER ROSALES
ELECTRICAL-Final 10/16/2025 Approved WILBER ROSALES
HVAC-Final 10/16/2025 Partial Approval WILBER ROSALES
ELECTRICAL-Final 10/24/2025 Approved WILBER ROSALES
Final 11/13/2025 Corrections Issued WILBER ROSALES
Green Building Final 11/13/2025 Conditional Approval WILBER ROSALES
HVAC-Final 11/13/2025 Not Ready for Inspection WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Required WILBER ROSALES
Final 12/10/2025 Not Ready for Inspection WILBER ROSALES
Green Building Final 12/10/2025 Not Ready for Inspection WILBER ROSALES
Service/Power Release 12/10/2025 Partial Inspection WILBER ROSALES
Final 12/15/2025 OK to Issue CofO WILBER ROSALES
Green Building Final 12/15/2025 Approved WILBER ROSALES
HVAC-Final 12/15/2025 Approved WILBER ROSALES
Service/Power Release 12/15/2025 Approved WILBER ROSALES