2023 S WALNUT AVE 90291

Certificate Information: 2023 S WALNUT AVE 90291

Application / Permit
24010-10000-01421
Plan Check / Job No.
B24LA05262
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 3/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 CARLOS MONTES
Corrections Issued 4/9/2024 CARLOS MONTES
Quality Review Completed 4/9/2024 GARO TELMI
Applicant returned to address corrections 5/3/2024 CARLOS MONTES
Plan Check Approved 10/22/2024 CARLOS MONTES
Issued 3/5/2025 APPLICANT
CofO in Progress 3/5/2026 RUBEN RIVAS
Permit Finaled 3/6/2026 RICHARD STEINBACH
CofO Issued 3/6/2026 RICHARD STEINBACH
Permit Finaled 3/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/22/2024 SARAH YOUSSEF
Permit Cleared 4/22/2024 ANDREA SAINT-ANTONIN
Address approval Cleared 4/23/2024 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 4/23/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 4/23/2024 ANDREA SAINT-ANTONIN
Hydrant and Access approval Cleared 5/31/2024 GILBERT URREA
Roof/Waste drainage to street Cleared 6/27/2024 ANDREA SAINT-ANTONIN
Trees in Parkway Cleared 7/8/2024 ADALBERTO VERA
Specific Plan Cleared 9/12/2024 PEDRO AYALA
Construction near power lines Cleared 10/7/2024 ENRIQUE ACOSTA
Excavation more than 5-ft deep Cleared 10/22/2024 CALOSHA APPROVED

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: NA23971       ,
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B       ,
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nguyen,, Huan; Lic. No.: NA64238       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/21/2025 Partial Approval JESUS RODRIGUEZ
Deputy Pre-Stress Concrete 4/30/2025 No Access for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/30/2025 Partial Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 4/30/2025 Partial Inspection JESUS RODRIGUEZ
Sewer 4/30/2025 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/19/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/19/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 7/16/2025 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 7/16/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/16/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 7/16/2025 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/12/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 8/12/2025 Approved JESUS RODRIGUEZ
Green Building Rough 8/25/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 8/25/2025 Not Ready for Inspection MICHAEL ALLEN
Wood Frame 8/25/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 8/26/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 8/26/2025 Approved MICHAEL ALLEN
Wood Frame 8/26/2025 Approved MICHAEL ALLEN
Insulation 9/2/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 9/9/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 10/7/2025 Approved JESUS RODRIGUEZ
Shower Pan 10/7/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/19/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Final 11/21/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 12/8/2025 Approved RUBEN RIVAS
PLUMBING-Final 1/12/2026 Approved RUBEN RIVAS
HVAC-Final 1/16/2026 Not Ready for Inspection RUBEN RIVAS
Final 1/21/2026 Not Ready for Inspection RUBEN RIVAS
Green Building Final 1/21/2026 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Not Required RUBEN RIVAS
Service/Power Release 1/21/2026 Corrections Issued RUBEN RIVAS
Smoke Detectors 1/21/2026 Approved RUBEN RIVAS
Final 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Service/Power Release 2/24/2026 Approved RUBEN RIVAS
Final 3/3/2026 OK to Issue CofO RUBEN RIVAS