2023 S WALNUT AVE 90291
Certificate Information: 2023 S WALNUT AVE 90291
- Application / Permit
- 24010-10000-01421
- Plan Check / Job No.
- B24LA05262
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/5/2025
- Issuing Office
- Current Status
- CofO Issued on 3/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | CARLOS MONTES |
| Corrections Issued | 4/9/2024 | CARLOS MONTES |
| Quality Review Completed | 4/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/3/2024 | CARLOS MONTES |
| Plan Check Approved | 10/22/2024 | CARLOS MONTES |
| Issued | 3/5/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | RUBEN RIVAS |
| Permit Finaled | 3/6/2026 | RICHARD STEINBACH |
| CofO Issued | 3/6/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/6/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/22/2024 | SARAH YOUSSEF |
| Permit | Cleared | 4/22/2024 | ANDREA SAINT-ANTONIN |
| Address approval | Cleared | 4/23/2024 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 4/23/2024 | ANDREA SAINT-ANTONIN |
| Hydrant and Access approval | Cleared | 5/31/2024 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | ANDREA SAINT-ANTONIN |
| Trees in Parkway | Cleared | 7/8/2024 | ADALBERTO VERA |
| Specific Plan | Cleared | 9/12/2024 | PEDRO AYALA |
| Construction near power lines | Cleared | 10/7/2024 | ENRIQUE ACOSTA |
| Excavation more than 5-ft deep | Cleared | 10/22/2024 | CALOSHA APPROVED |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/21/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Pre-Stress Concrete | 4/30/2025 | No Access for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Partial Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/30/2025 | Partial Inspection | JESUS RODRIGUEZ |
| Sewer | 4/30/2025 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/19/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 7/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 7/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/16/2025 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/16/2025 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/12/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/12/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/25/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 8/25/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Wood Frame | 8/25/2025 | Corrections Issued | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 8/26/2025 | Approved | MICHAEL ALLEN |
| Wood Frame | 8/26/2025 | Approved | MICHAEL ALLEN |
| Insulation | 9/2/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/9/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 10/7/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/7/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/19/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Final | 11/21/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 12/8/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 1/12/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 1/16/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Final | 1/21/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Green Building Final | 1/21/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Not Required | RUBEN RIVAS |
| Service/Power Release | 1/21/2026 | Corrections Issued | RUBEN RIVAS |
| Smoke Detectors | 1/21/2026 | Approved | RUBEN RIVAS |
| Final | 2/24/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Service/Power Release | 2/24/2026 | Approved | RUBEN RIVAS |
| Final | 3/3/2026 | OK to Issue CofO | RUBEN RIVAS |