EPLAN NEW 3-STORY DUPLEX WITH 4-CAR GARAGE AND ATTACHED ADU REAR BUILDING
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
CofO Issued on 5/31/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2024 APPLICANT
Assigned to Zoning Architect 3/14/2024 JASON BRAVO
Assigned to Plan Check Engineer 3/28/2024 CARLOS MONTES
Corrections Issued 4/3/2024 CARLOS MONTES
Quality Review Completed 4/3/2024 GARO TELMI
Applicant returned to address corrections 3/27/2025 CARLOS MONTES
Applicant returned to address corrections 4/30/2025 CARLOS MONTES
Plan Check Approved 5/20/2025 CARLOS MONTES
Issued 6/4/2025 APPLICANT
CofO in Progress 5/30/2026 SABAS ALONSO
Permit Finaled 5/31/2026 DEROLD HAUFF
CofO Issued 5/31/2026 DEROLD HAUFF
Permit Finaled 5/31/2026 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 5/15/2024 MANERI ROMAN
ZI Cleared 5/15/2024 MANERI ROMAN
Address approval Cleared 5/16/2024 CELINA MORENO
Highway dedication Cleared 5/16/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/21/2024 CELINA MORENO
Sewer availability Cleared 5/21/2024 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 6/7/2024 DANIEL CORONADO
Miscellaneous Cleared 6/7/2024 DANIEL CORONADO
SB8 RUD Cleared 6/21/2024 ALYSSA FLORES
Hydrant and Access approval Cleared 11/12/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 12/9/2024 ERNEST TSE
DAS Clearance Cleared 2/3/2025 ELIZABETH TOMS
Roof/Waste drainage to street Cleared 2/13/2025 CELINA MORENO
Green Code Cleared 5/20/2025 CARLOS MONTES
Zoning Plan Check Cleared 5/20/2025 CARLOS MONTES

Contact Information

Contractor Maven Construction; Lic. No.: 1094032-B       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/14/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 8/27/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 9/5/2025 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/17/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 9/17/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 12/4/2025 Partial Approval SABAS ALONSO
Deputy Wood Construction 12/9/2025 Conditional Approval DEVON JACKSON
HVAC-Rough 12/10/2025 Approved SABAS ALONSO
PLUMBING-Rough 12/10/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/26/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 1/5/2026 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/6/2026 Approved SABAS ALONSO
Green Building Rough 1/6/2026 Approved SABAS ALONSO
Insulation 1/6/2026 Approved SABAS ALONSO
Verify Sprinkler Sign Off 1/6/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Approved SABAS ALONSO
Drywall Nailing 1/12/2026 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 1/14/2026 Approved SABAS ALONSO
Drywall Nailing 1/20/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 1/20/2026 Approved SABAS ALONSO
Shower Pan 1/29/2026 Corrections Issued SABAS ALONSO
Sewer 2/17/2026 Approved SABAS ALONSO
Shower Pan 2/17/2026 Approved SABAS ALONSO
Underground Mechanical 2/17/2026 Partial Approval SABAS ALONSO
Underground Mechanical 2/24/2026 Approved SABAS ALONSO
ELECTRICAL-Final 5/6/2026 Approved SABAS ALONSO
Final 5/6/2026 Not Ready for Inspection SABAS ALONSO
Gas Test 5/6/2026 Approved SABAS ALONSO
Green Building Final 5/6/2026 Approved SABAS ALONSO
HVAC-Final 5/6/2026 Approved SABAS ALONSO
PLUMBING-Final 5/6/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 5/6/2026 Approved SABAS ALONSO
Smoke Detectors 5/6/2026 Approved SABAS ALONSO
Final 5/21/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/27/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 5/27/2026 Approved SABAS ALONSO