1177 W LEIGHTON AVE 90037
Certificate Information: 1177 W LEIGHTON AVE 90037
- Application / Permit
- 24010-10000-01367
- Plan Check / Job No.
- B24LA04663
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN NEW 3-STORY DUPLEX WITH 4-CAR GARAGE AND ATTACHED ADU REAR BUILDING
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- CofO Issued on 5/31/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2024 | APPLICANT |
| Assigned to Zoning Architect | 3/14/2024 | JASON BRAVO |
| Assigned to Plan Check Engineer | 3/28/2024 | CARLOS MONTES |
| Corrections Issued | 4/3/2024 | CARLOS MONTES |
| Quality Review Completed | 4/3/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/27/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 4/30/2025 | CARLOS MONTES |
| Plan Check Approved | 5/20/2025 | CARLOS MONTES |
| Issued | 6/4/2025 | APPLICANT |
| CofO in Progress | 5/30/2026 | SABAS ALONSO |
| Permit Finaled | 5/31/2026 | DEROLD HAUFF |
| CofO Issued | 5/31/2026 | DEROLD HAUFF |
| Permit Finaled | 5/31/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/15/2024 | MANERI ROMAN |
| ZI | Cleared | 5/15/2024 | MANERI ROMAN |
| Address approval | Cleared | 5/16/2024 | CELINA MORENO |
| Highway dedication | Cleared | 5/16/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | CELINA MORENO |
| Sewer availability | Cleared | 5/21/2024 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 6/7/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 6/7/2024 | DANIEL CORONADO |
| SB8 RUD | Cleared | 6/21/2024 | ALYSSA FLORES |
| Hydrant and Access approval | Cleared | 11/12/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 12/9/2024 | ERNEST TSE |
| DAS Clearance | Cleared | 2/3/2025 | ELIZABETH TOMS |
| Roof/Waste drainage to street | Cleared | 2/13/2025 | CELINA MORENO |
| Green Code | Cleared | 5/20/2025 | CARLOS MONTES |
| Zoning Plan Check | Cleared | 5/20/2025 | CARLOS MONTES |
Contact Information
| Contractor | Maven Construction; Lic. No.: 1094032-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/14/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/27/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/17/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 12/4/2025 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 12/9/2025 | Conditional Approval | DEVON JACKSON |
| HVAC-Rough | 12/10/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/10/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/26/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/5/2026 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 1/6/2026 | Approved | SABAS ALONSO |
| Insulation | 1/6/2026 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 1/6/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/12/2026 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 1/14/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/20/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/20/2026 | Approved | SABAS ALONSO |
| Shower Pan | 1/29/2026 | Corrections Issued | SABAS ALONSO |
| Sewer | 2/17/2026 | Approved | SABAS ALONSO |
| Shower Pan | 2/17/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/17/2026 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 2/24/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/6/2026 | Approved | SABAS ALONSO |
| Final | 5/6/2026 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 5/6/2026 | Approved | SABAS ALONSO |
| Green Building Final | 5/6/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 5/6/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 5/6/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 5/6/2026 | Approved | SABAS ALONSO |
| Smoke Detectors | 5/6/2026 | Approved | SABAS ALONSO |
| Final | 5/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/27/2026 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 5/27/2026 | Approved | SABAS ALONSO |