2134 W NORWALK AVE 90041

Certificate Information: 2134 W NORWALK AVE 90041

Application / Permit
24010-10000-01316
Plan Check / Job No.
B24LA05865
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. NEW 1 STORY DETACHED ADU PER STATE LAW AND GCS 65852.2(e)(1)(B) and LAMC 12.22 A33(c)(d)&(g).
Permit Issued
Issued on 10/29/2024
Issuing Office
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2024 APPLICANT
Assigned to Plan Check Engineer 4/10/2024 ZAW HAN
Corrections Issued 4/11/2024 ZAW HAN
Applicant returned to address corrections 10/2/2024 ZAW HAN
Plan Check Approved 10/8/2024 SAMUEL GONZALEZ
Issued 10/29/2024 APPLICANT
CofO in Progress 8/21/2025 ALIZAH MAYAGOITIA
Permit Finaled 8/22/2025 DEROLD HAUFF
CofO Issued 8/22/2025 DEROLD HAUFF
Permit Finaled 8/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/5/2024 JUSTIN BICOL
Construction near power lines Cleared 9/5/2024 WALTER RAMIREZ
Construction within easement Cleared 9/5/2024 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 9/6/2024 WALLIE JONG
Grading Pre-Inspection Cleared 9/6/2024 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 9/18/2024 JUSTIN BICOL
Sewer availability Cleared 9/18/2024 JUSTIN BICOL
GPI Written Notices Cleared 10/8/2024 ZAW HAN

Contact Information

Contractor Affordable Building Solutions Inc; Lic. No.: 1068574-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2024 Partial Approval ROY SPAULDING
PLUMBING-Rough 11/12/2024 Approved ROY SPAULDING
Footing/Foundation/Slab 11/15/2024 Approved ROY SPAULDING
Deputy Wood Construction 11/26/2024 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 12/12/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 12/12/2024 Not Ready for Inspection ROY SPAULDING
Green Building Rough 12/12/2024 Approved ROY SPAULDING
HVAC-Rough 12/12/2024 Corrections Issued ROY SPAULDING
Interior/Exterior Lathing 12/12/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 12/12/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 12/12/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 12/20/2024 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/20/2024 Approved JOAQUIN GREENOUGH
HVAC-Rough 12/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/26/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 1/7/2025 Approved BRENDAN MORELLI
HVAC-Rough 1/7/2025 Approved BRENDAN MORELLI
Insulation 1/7/2025 Corrections Issued BRENDAN MORELLI
Insulation 1/21/2025 Approved STUART CHAPMAN
Drywall Nailing 1/31/2025 Approved STUART CHAPMAN
Sewer 4/17/2025 Approved DAVID WILLIAMS
HVAC-Final 5/28/2025 Corrections Issued DAVID WILLIAMS
PLUMBING-Final 5/28/2025 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Final 6/11/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 6/11/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 6/11/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 6/30/2025 Approved DAVID WILLIAMS
PLUMBING-Final 6/30/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
Final 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Not Ready JEFFREY MEAD
ELECTRICAL-Final 8/20/2025 Approved ALIZAH MAYAGOITIA
Final 8/20/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 8/20/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 8/20/2025 Approved ALIZAH MAYAGOITIA
Smoke Detectors 8/20/2025 Approved ALIZAH MAYAGOITIA