242 1/4-1/2 W 89TH ST 90003
Certificate Information: 242 1/4-1/2 W 89TH ST 90003
- Application / Permit
- 24010-10000-01297
- Plan Check / Job No.
- B24LA05788
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2 story 2 unit ADU in rear of existing multiple family lot. per LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/12/2024
- Issuing Office
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 4/6/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/15/2024 | YOUNG KIM |
| Plan Check Approved | 7/2/2024 | ARSALAN SHABESTARI |
| Issued | 8/12/2024 | APPLICANT |
| CofO in Progress | 12/10/2025 | JOHN QUINTANILLA |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
| CofO Issued | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/22/2024 | ROGELIO CORTES |
| Address approval | Cleared | 4/26/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/26/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/1/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 12/12/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/24/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/2/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Conditional Approval | JOHN QUINTANILLA |
| Deputy Wood Construction | 1/27/2025 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 2/18/2025 | Partial Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 2/20/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/3/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 4/11/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/17/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| MERV13>=Rough | 4/17/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 4/17/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 5/19/2025 | Approved | MICHAEL LEWIS |
| Insulation | 5/29/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Insulation | 6/2/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 6/11/2025 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 6/16/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 6/27/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 7/15/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 7/23/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 8/25/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Service/Power Release | 8/27/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Final | 9/9/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Final | 9/9/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 9/9/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 9/9/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 9/15/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 9/16/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 9/16/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Final | 9/16/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 9/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| MERV13>=Final | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Final | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 9/22/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | JOHN QUINTANILLA |
| Final | 10/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 10/17/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 10/17/2025 | Approved | JOHN QUINTANILLA |
| MERV13>=Final | 10/17/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 10/17/2025 | Partial Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 10/17/2025 | Approved | JOHN QUINTANILLA |
| Final | 10/23/2025 | Conditional Approval | JOHN QUINTANILLA |
| Service/Power Release | 10/23/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/1/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 12/9/2025 | OK to Issue CofO | JOHN QUINTANILLA |