1126 W 61ST ST 90044
Certificate Information: 1126 W 61ST ST 90044
- Application / Permit
- 24010-10000-01295
- Plan Check / Job No.
- B24LA05776
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY DETACHED ADU PER ENGINEER DETAILS (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2024 | AUNG SOE |
| Corrections Issued | 4/9/2024 | AUNG SOE |
| Building Plans Picked Up | 4/15/2024 | APPLICANT |
| Applicant returned to address corrections | 6/24/2024 | ALEXANDER JOO |
| Plan Check Approved | 7/29/2024 | ALEXANDER JOO |
| Issued | 7/29/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | BARRY HACHE |
| Permit Finaled | 9/1/2025 | DEROLD HAUFF |
| CofO Issued | 9/1/2025 | DEROLD HAUFF |
| Permit Finaled | 9/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2024 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 6/25/2024 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/23/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 12/11/2024 | Corrections Issued | JOSE MACIAS |
| Verify Sprinkler Sign Off | 12/11/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 12/24/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/24/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 12/24/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 12/24/2024 | Approved | JOSE MACIAS |
| Insulation | 12/31/2024 | Corrections Issued | BARRY HACHE |
| Insulation | 1/3/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 1/17/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 1/17/2025 | Approved | BARRY HACHE |
| Shower Pan | 1/17/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 2/14/2025 | Approved | BARRY HACHE |
| Final | 5/21/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 5/21/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 7/8/2025 | Corrections Issued | BARRY HACHE |
| Final | 7/8/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 7/8/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 7/8/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 7/8/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 7/8/2025 | Approved | BARRY HACHE |
| Service/Power Release | 7/24/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 7/30/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 7/30/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 7/30/2025 | Approved | BARRY HACHE |
| HVAC-Final | 7/30/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 7/30/2025 | Corrections Issued | BARRY HACHE |
| Service/Power Release | 7/30/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/14/2025 | Corrections Issued | BARRY HACHE |
| Final | 8/14/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 8/14/2025 | Approved | BARRY HACHE |
| Service/Power Release | 8/14/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/26/2025 | Approved | BARRY HACHE |
| Final | 8/26/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 8/29/2025 | OK to Issue CofO | BARRY HACHE |
| Service/Power Release | 8/29/2025 | Approved | BARRY HACHE |