1250 N CAPRI DR 90272

Certificate Information: 1250 N CAPRI DR 90272

Application / Permit
24010-10000-01286
Plan Check / Job No.
B24LA05751
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW 9' x 13' SECURITY BOOTH, AND REVISE THE # OF PROVIDED PARKING, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/23/2025
Issuing Office
Current Status
CofO Issued on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 RARES BODEA
Assigned to Zoning Architect 4/4/2024 FRANCIS AHN
Corrections Issued 4/7/2024 SEAN SHAHMIRI
Quality Review Completed 4/9/2024 STEVEN KIM
Applicant returned to address corrections 5/24/2024 SEAN SHAHMIRI
Applicant returned to address corrections 4/17/2025 RARES BODEA
Plan Check Approved 4/21/2025 RARES BODEA
Issued 4/23/2025 APPLICANT
CofO in Progress 2/13/2026 DANIEL VARNUM
Permit Finaled 2/27/2026 VASIL MIHALEV
Permit Finaled 2/27/2026 VASIL MIHALEV
CofO Issued 2/27/2026 VASIL MIHALEV

Permit Application Clearance Information

Address approval Cleared 4/15/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/15/2024 HISASHI KOBAYAKAWA
Watercourse Cleared 4/15/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/16/2024 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 5/21/2024 VASIL MIHALEV
ZA Case Cleared 5/22/2024 ASHLEY RODARTE
Green Code Cleared 6/26/2024 Fernando Flores
DAS Clearance Cleared 8/15/2024 ELIZABETH TOMS
Low Impact Development (LID) Cleared 12/12/2024 MARTIN FRAGOSO
Zoning Plan Check Cleared 4/3/2025 Fernando Flores

Contact Information

Architect Sanchez,, Gabriel; Lic. No.: NA26771       ,
Contractor Dorado Design And Construction Inc; Lic. No.: 778969-B       ,
Engineer Stinchcomb,, Ingrid Sonia; Lic. No.: C44759 5525 GOSS ROAD      PHELAN, CA 92371

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2025 Approved DANIEL VARNUM
Green Building Rough 8/13/2025 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 8/13/2025 Not Ready for Inspection DANIEL VARNUM
Wood Frame 8/13/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 8/26/2025 Approved DANIEL VARNUM
Verify Sprinkler Sign Off 8/26/2025 Approved DANIEL VARNUM
Wood Frame 8/26/2025 Approved DANIEL VARNUM
Drywall Nailing 9/3/2025 Approved DERRICK SPENCER
Interior/Exterior Lathing 9/15/2025 Approved VASIL MIHALEV
Final 1/2/2026 Not Ready for Inspection DANIEL VARNUM
Green Building Final 1/2/2026 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 1/2/2026 SGSOV No Gas DANIEL VARNUM
Smoke Detectors 1/2/2026 Approved DANIEL VARNUM
Final 1/13/2026 Not Ready for Inspection DANIEL VARNUM
Final 2/17/2026 OK to Issue CofO DANIEL VARNUM