1837 1/2 N SICHEL ST 90031
Certificate Information: 1837 1/2 N SICHEL ST 90031
- Application / Permit
- 24010-10000-01240
- Plan Check / Job No.
- B24LA05553
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN. NEW 2-STORY ADU Per LAMC 12.22 A.33 (c)-(d) the building will be fire sprinkler with NFPA-13D
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 7/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 5/9/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 5/21/2024 | RODOLFO ARIAS |
| Plan Check Approved | 1/16/2025 | GEORGE JOLAKIAN |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 6/30/2026 | OSVALDO PARAMO |
| Permit Finaled | 7/6/2026 | DEROLD HAUFF |
| CofO Issued | 7/6/2026 | DEROLD HAUFF |
| Permit Finaled | 7/6/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/17/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2024 | JEANIE LAM |
| Sewer availability | Cleared | 8/1/2024 | JEANIE LAM |
| Construction near power lines | Cleared | 8/27/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/12/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole; Lic. No.: C63361 | 1620 CENTINELA AVE 304B INGLEWOOD, CA 90302 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/1/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/23/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Corrections Issued | JOHN QUINTANILLA |
| Deputy Wood Construction | 7/23/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 8/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 8/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 8/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 8/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/25/2025 | Corrections Issued | ANTHONY RAMOS |
| ELECTRICAL-Rough | 10/2/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/10/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/10/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/10/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/19/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 12/19/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 12/19/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/19/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/23/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/6/2026 | Approved | ANTHONY RAMOS |
| Shower Pan | 1/13/2026 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/16/2026 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/29/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/29/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/29/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/6/2026 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/6/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | OSVALDO PARAMO |
| Final | 5/8/2026 | Corrections Issued | OSVALDO PARAMO |
| Gas Test | 5/8/2026 | Approved | OSVALDO PARAMO |
| Green Building Final | 5/8/2026 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 5/8/2026 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 5/8/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 5/8/2026 | Approved | OSVALDO PARAMO |
| Final | 6/16/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 6/16/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 6/25/2026 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/25/2026 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 6/25/2026 | Approved | OSVALDO PARAMO |