1677 E IMPERIAL HWY 90059
Certificate Information: 1677 E IMPERIAL HWY 90059
- Application / Permit
- 24010-10000-01195
- Plan Check / Job No.
- B24LA05274
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Metro
- Current Status
- Issued on 12/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | JAD BASMA |
| Corrections Issued | 3/30/2024 | JAD BASMA |
| Quality Review Completed | 4/5/2024 | KEN GILL |
| Building Plans Picked Up | 4/26/2024 | APPLICANT |
| Plan Check Approved | 11/27/2024 | JAD BASMA |
| Issued | 12/6/2024 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/6/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/17/2024 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/21/2024 | JESSICA OPINION |
| Address approval | Cleared | 11/1/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 11/1/2024 | JESSICA OPINION |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/30/2025 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/25/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/25/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 11/5/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 11/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 11/6/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 12/4/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/4/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 12/18/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/15/2026 | Approved | ARTHUR NEGRETE |
| Green Building Final | 4/15/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/15/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/15/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/15/2026 | Approved | ARTHUR NEGRETE |
| Sewer | 4/15/2026 | Approved | ARTHUR NEGRETE |