3567 1/2 E 8TH ST 90023

Certificate Information: 3567 1/2 E 8TH ST 90023

Application / Permit
24010-10000-01182
Plan Check / Job No.
B24LA05186
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached ADU per LAMC 12.22 A.33 (c) and (d). Design per WFPP.
Permit Issued
Issued on 3/16/2025
Issuing Office
Current Status
CofO Issued on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 CAROLEAN BASMA
Corrections Issued 3/29/2024 CAROLEAN BASMA
Applicant returned to address corrections 2/21/2025 DAVID CASTILLO
Applicant returned to address corrections 2/26/2025 AMY GUEVARRA
Applicant returned to address corrections 3/6/2025 AMY GUEVARRA
Plan Check Approved 3/14/2025 AMY GUEVARRA
Issued 3/16/2025 APPLICANT
CofO in Progress 2/26/2026 FREDDIE RIVERA
Permit Finaled 2/27/2026 DEROLD HAUFF
CofO Issued 2/27/2026 DEROLD HAUFF
Permit Finaled 2/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/20/2024 RICARDO BOHORQUEZ
Address approval Cleared 7/12/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 8/6/2024 JEANIE LAM
Sewer availability Cleared 9/18/2024 MICHELLE RIOS
Clean Up Green Up Cleared 9/30/2024 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 10/3/2024 WALLIE JONG
Construction near power lines Cleared 1/15/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/20/2025 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 3/24/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/24/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 3/24/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 3/28/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 4/9/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/21/2025 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved FREDDIE RIVERA
MERV13>=Rough 4/21/2025 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 4/21/2025 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/28/2025 Approved FREDDIE RIVERA
ELECTRICAL-Rough 4/28/2025 Approved FREDDIE RIVERA
Green Building Rough 4/28/2025 Approved FREDDIE RIVERA
HVAC-Rough 4/28/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/28/2025 Partial Approval FREDDIE RIVERA
MERV13>=Rough 4/28/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 4/28/2025 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 4/28/2025 Approved FREDDIE RIVERA
Sewer 5/1/2025 Approved ANTHONY RAMOS
Insulation 5/5/2025 Partial Approval REGINA MENDEZ
Drywall Nailing 5/6/2025 Approved FREDDIE RIVERA
Final 10/22/2025 Corrections Issued FREDDIE RIVERA
MERV13>=Final 10/22/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 10/22/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/22/2025 Approved FREDDIE RIVERA
Final 2/25/2026 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/25/2026 Approved FREDDIE RIVERA