3567 1/2 E 8TH ST 90023
Certificate Information: 3567 1/2 E 8TH ST 90023
- Application / Permit
- 24010-10000-01182
- Plan Check / Job No.
- B24LA05186
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached ADU per LAMC 12.22 A.33 (c) and (d). Design per WFPP.
- Permit Issued
- Issued on 3/16/2025
- Issuing Office
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | CAROLEAN BASMA |
| Corrections Issued | 3/29/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 2/21/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/26/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/6/2025 | AMY GUEVARRA |
| Plan Check Approved | 3/14/2025 | AMY GUEVARRA |
| Issued | 3/16/2025 | APPLICANT |
| CofO in Progress | 2/26/2026 | FREDDIE RIVERA |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| CofO Issued | 2/27/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/20/2024 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 7/12/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | JEANIE LAM |
| Sewer availability | Cleared | 9/18/2024 | MICHELLE RIOS |
| Clean Up Green Up | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 1/15/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/20/2025 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/24/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 3/24/2025 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/28/2025 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/9/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/21/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 4/21/2025 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/21/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/28/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/28/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 4/28/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 4/28/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/28/2025 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | FREDDIE RIVERA |
| Sewer | 5/1/2025 | Approved | ANTHONY RAMOS |
| Insulation | 5/5/2025 | Partial Approval | REGINA MENDEZ |
| Drywall Nailing | 5/6/2025 | Approved | FREDDIE RIVERA |
| Final | 10/22/2025 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 10/22/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 10/22/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/22/2025 | Approved | FREDDIE RIVERA |
| Final | 2/25/2026 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 2/25/2026 | Approved | FREDDIE RIVERA |