8125 W GOULD AVE 90046
Certificate Information: 8125 W GOULD AVE 90046
- Application / Permit
- 24010-10000-01176
- Plan Check / Job No.
- B23LA24899
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- eplan: NEW 2-story Accessory Living Quarters
- Permit Issued
- Issued on 9/26/2025
- Issuing Office
- Current Status
- Issued on 9/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | KHEDER ALRAZAA |
| Corrections Issued | 4/12/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 4/16/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/8/2025 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 8/28/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 9/26/2025 | KHEDER ALRAZAA |
| Issued | 9/26/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/16/2024 | KHEDER ALRAZAA |
| Grading Pre-Inspection | Cleared | 4/16/2024 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 6/23/2025 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 7/14/2025 | KENNETH FRASER |
| Low Impact Development (LID) | Cleared | 8/5/2025 | DANIEL LEON-MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/6/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/9/2026 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/14/2026 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 1/14/2026 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 2/23/2026 | Approved | ROY SPAULDING |
| Drywall Nailing | 3/31/2026 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 5/8/2026 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Partial Approval | ROY SPAULDING |
| Wood Frame | 5/8/2026 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 5/19/2026 | Approved | ROY SPAULDING |
| Underground Mechanical | 5/19/2026 | Partial Approval | ROY SPAULDING |