3541 1/2 E 8TH ST 90023

Certificate Information: 3541 1/2 E 8TH ST 90023

Application / Permit
24010-10000-01167
Plan Check / Job No.
B24LA05072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 15'-3" X 32'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
Issued on 1/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/20/2024 APPLICANT
Assigned to Plan Check Engineer 3/27/2024 ALEC MOUSAKHANIAN
Corrections Issued 3/27/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 12/5/2024 ALEC MOUSAKHANIAN
Plan Check Approved 12/8/2024 ALEC MOUSAKHANIAN
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/2/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 8/15/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 8/15/2024 AMBER CAMPBELL
Sewer availability Cleared 8/15/2024 AMBER CAMPBELL
ZI Cleared 9/25/2024 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/29/2025 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/3/2025 Approved FREDDIE RIVERA
Special/Order Compliance 2/3/2025 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 3/3/2025 Approved FREDDIE RIVERA
Wood Frame 3/5/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/7/2025 Approved OSVALDO PARAMO
Green Building Rough 3/7/2025 Approved OSVALDO PARAMO
Insulation 3/7/2025 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Rough 3/7/2025 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 3/7/2025 Approved OSVALDO PARAMO
Insulation 3/11/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/11/2025 Partial Approval FREDDIE RIVERA
Drywall Nailing 3/13/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/13/2025 Approved FREDDIE RIVERA
Sewer 3/27/2025 Approved FREDDIE RIVERA
Final 6/5/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 6/5/2025 Partial Inspection FREDDIE RIVERA
MERV13>=Final 6/5/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 6/5/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 6/5/2025 Approved FREDDIE RIVERA
Final 6/26/2025 Conditional Approval FREDDIE RIVERA
Green Building Final 6/26/2025 Approved FREDDIE RIVERA
Service/Power Release 6/26/2025 Approved FREDDIE RIVERA