1555 W 37TH ST 90018
Certificate Information: 1555 W 37TH ST 90018
- Application / Permit
- 24010-10000-01162
- Plan Check / Job No.
- B24LA05027
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 32' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 3/26/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/11/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 8/22/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/28/2024 | GIOVANNY CHAVEZ |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 10/14/2025 | SABAS ALONSO |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/28/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 4/1/2024 | TREVOR QUAN |
| ZA Case | Cleared | 4/1/2024 | YINGSHI HUANG |
| Low Impact Development (LID) | Cleared | 8/20/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/27/2024 | WALLIE JONG |
Contact Information
| Contractor | Aligcus Construction Llc; Lic. No.: 1105980-B | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/22/2024 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 11/13/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 11/27/2024 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/25/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/27/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 2/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 3/13/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/13/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/13/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 3/13/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/28/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/28/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/15/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Insulation | 4/15/2025 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/15/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 4/15/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/18/2025 | Approved | ANTHONY RAMOS |
| Insulation | 4/18/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 7/15/2025 | Corrections Issued | SABAS ALONSO |
| Final | 10/3/2025 | Corrections Issued | BARRY HACHE |
| Smoke Detectors | 10/3/2025 | Approved | BARRY HACHE |
| Final | 10/8/2025 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 10/8/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 10/8/2025 | Approved | SABAS ALONSO |