7510 N ETIWANDA AVE 91335
Certificate Information: 7510 N ETIWANDA AVE 91335
- Application / Permit
- 24010-10000-01139
- Plan Check / Job No.
- B24LA04964
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****ePlan**** New 2-story ADU (1,190 sf) at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | REZA HAGHIGHAT |
| Corrections Issued | 3/22/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 4/2/2024 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/24/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 7/6/2024 | REZA HAGHIGHAT |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 8/26/2025 | JUAN ALVARADO |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 3/27/2024 | KENIA CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2024 | KENIA CASTILLO |
| Sewer availability | Cleared | 3/29/2024 | KENIA CASTILLO |
| Hydrant and Access approval | Cleared | 4/26/2024 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 4/26/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 5/3/2024 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 6/28/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Naeem,, Samer; Lic. No.: C88038 | 804 ARDEN AVE GLENDALE, CA 91202 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 7/31/2024 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 10/10/2024 | Corrections Issued | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/13/2025 | Partial Approval | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/13/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/23/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 2/18/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/25/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 2/25/2025 | Approved | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 2/25/2025 | Approved | JUAN ALVARADO |
| Insulation | 3/3/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 3/3/2025 | Approved | JUAN ALVARADO |
| Insulation | 3/6/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 3/14/2025 | Approved | JUAN ALVARADO |
| Final | 6/20/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 6/20/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 6/20/2025 | Approved | JUAN ALVARADO |
| Final | 7/25/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 7/25/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 8/22/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 8/22/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 8/22/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 8/22/2025 | Approved | JUAN ALVARADO |