1619 S ROBERTSON BLVD 90035
Certificate Information: 1619 S ROBERTSON BLVD 90035
- Application / Permit
- 24010-10000-01088
- Plan Check / Job No.
- B24LA04822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW SHADE STRUCTURE, LOCATED IN THE EXISTING PATIO OF HIGH SCHOOL.
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/5/2024
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 3/21/2024 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/23/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 3/28/2024 | PETER KIM |
| Disabled Access Plans Picked Up | 4/2/2024 | APPLICANT |
| Building Plans Picked Up | 4/18/2024 | APPLICANT |
| Plan Check Approved | 7/29/2024 | SALVADOR QUINTANILLA |
| Issued | 8/6/2024 | APPLICANT |
| Permit Finaled | 11/6/2024 | DANIEL VARNUM |
Permit Application Clearance Information
| Green Code | Cleared | 3/15/2024 | MICHAEL AYERS |
| Highway dedication | Cleared | 5/13/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/13/2024 | WALLIE JONG |
| ZA Case | Cleared | 5/13/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2024 | WALLIE JONG |
| ZA Case | Cleared | 5/17/2024 | DANIEL CORONADO |
| Grading Pre-Inspection | Cleared | 6/20/2024 | SALVADOR QUINTANILLA |
| DAS Clearance | Cleared | 6/24/2024 | SALVADOR QUINTANILLA |
| Fire Marshal Fire Life Safety | Cleared | 7/24/2024 | FIRE DEPARTMENT |
| Zoning Plan Check | Cleared | 7/29/2024 | SALVADOR QUINTANILLA |
Contact Information
| Contractor | Driver S P G Llc; Lic. No.: 960119-B | 468 NORTH ROSEMEAD BLVD PASADENA, CA 91107 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/20/2024 | Approved | PAUL DAVIDSON |
| METHANE-Barrier | 8/20/2024 | Approved | PAUL DAVIDSON |
| METHANE-Subgrade | 8/20/2024 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 8/21/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Other (see comments) | 8/22/2024 | Conditional Approval | PAUL DAVIDSON |
| Final | 10/21/2024 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Final | 10/21/2024 | Approved | DANIEL VARNUM |
| METHANE-Rough | 10/21/2024 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 10/21/2024 | Approved | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 10/21/2024 | Approved | DANIEL VARNUM |
| Wood Frame | 10/21/2024 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 11/6/2024 | Partial Approval | DANIEL VARNUM |
| Final | 11/6/2024 | Permit Finaled | DANIEL VARNUM |