127 E 118TH ST 90061
Certificate Information: 127 E 118TH ST 90061
- Application / Permit
- 24010-10000-01058
- Plan Check / Job No.
- B24LA04657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- EPLAN: NEW 25' x 21' DETACHED GARAGE. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Current Status
- CofO Issued on 12/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/20/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/12/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/16/2024 | MIROOSH KHACHATOORIAN |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 12/9/2025 | BEN MOLSTAD |
| Permit Finaled | 12/10/2025 | ANSON MAGLASANG |
| CofO Issued | 12/10/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/10/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/22/2024 | PATRICK LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 4/24/2024 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 8/2/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: NA64738 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2025 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/6/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/7/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/11/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/18/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/20/2025 | Partial Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/27/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/3/2025 | Approved | ANTHONY EGSON |
| Wood Frame | 5/23/2025 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 6/10/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/10/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 6/18/2025 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/5/2025 | No Access for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/8/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | BEN MOLSTAD |
| Final | 10/22/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 10/22/2025 | Approved | BEN MOLSTAD |
| Green Building Rough | 10/22/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 10/22/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 10/28/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Special/Order Compliance | 11/4/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 12/8/2025 | OK to Issue CofO | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 12/8/2025 | Approved | BEN MOLSTAD |
| Smoke Detectors | 12/8/2025 | Approved | BEN MOLSTAD |