4139 1/2 S 3RD AVE 90008

Certificate Information: 4139 1/2 S 3RD AVE 90008

Application / Permit
24010-10000-01040
Plan Check / Job No.
B24LA04526
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ADU STUDIO ADDITION (24'2" X 15'7") TO (E) GARAGE PER LAMC 12.22 A.33(c) AND (D)
Permit Issued
Issued on 5/20/2024
Issuing Office
Current Status
CofO Issued on 1/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 NGHI SU
Corrections Issued 3/16/2024 NGHI SU
Applicant returned to address corrections 4/11/2024 ZAW HAN
Applicant returned to address corrections 4/13/2024 ZAW HAN
Applicant returned to address corrections 4/17/2024 ZAW HAN
Plan Check Approved 5/16/2024 JOSEPH RAFOLS
Issued 5/20/2024 APPLICANT
CofO in Progress 12/11/2024 BARRY HACHE
Permit Finaled 1/11/2025 DEROLD HAUFF
CofO Issued 1/11/2025 DEROLD HAUFF
Permit Finaled 1/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/8/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 4/8/2024 WALLIE JONG
Sewer availability Cleared 4/8/2024 WALLIE JONG
Construction near power lines Cleared 5/8/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Bustillos, Portillo, Alejandro; Lic. No.: C87257 4749 W 169TH STREET      LAWNDALE, CA 90260

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/30/2024 Corrections Issued ANTHONY EGSON
Sewer 7/30/2024 Approved ANTHONY EGSON
Underground Mechanical 7/30/2024 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/6/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 8/6/2024 Corrections Issued ANTHONY EGSON
Grounding or Bonding 8/6/2024 Approved ANTHONY EGSON
Underground Mechanical 8/6/2024 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 8/8/2024 Approved ANTHONY EGSON
Deputy Reinf. Concrete 8/12/2024 Conditional Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 8/19/2024 Partial Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 10/1/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 10/1/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 10/1/2024 Approved ANTHONY EGSON
HVAC-Rough 10/1/2024 Approved ANTHONY EGSON
PLUMBING-Rough 10/1/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/7/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 10/7/2024 Partial Approval AMIR NAZARIAN
PLUMBING-Rough 10/7/2024 Approved AMIR NAZARIAN
Insulation 10/11/2024 Approved ANTHONY EGSON
Shower Pan 10/11/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/16/2024 Approved ANTHONY EGSON
Drywall Nailing 10/16/2024 Approved ANTHONY EGSON
Green Building Rough 10/16/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/16/2024 Approved ANTHONY EGSON
Final 11/21/2024 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 11/21/2024 Not Ready for Inspection BARRY HACHE
Green Building Final 11/21/2024 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Not Ready BARRY HACHE
Smoke Detectors 11/21/2024 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 11/25/2024 Corrections Issued BARRY HACHE
HVAC-Final 11/25/2024 Approved BARRY HACHE
Protected Tree Letter 11/25/2024 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready BARRY HACHE
Smoke Detectors 11/25/2024 Corrections Issued BARRY HACHE
Final 12/5/2024 Not Ready for Inspection BARRY HACHE
Footing/Foundation/Slab 12/5/2024 Approved BARRY HACHE
Green Building Final 12/5/2024 Approved BARRY HACHE
PLUMBING-Final 12/5/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Not Required BARRY HACHE
Smoke Detectors 12/5/2024 Approved BARRY HACHE
Final 12/11/2024 OK to Issue CofO BARRY HACHE