3876-3876 1/2 E YORK BLVD 90065
Certificate Information: 3876-3876 1/2 E YORK BLVD 90065
- Application / Permit
- 24010-10000-01033
- Plan Check / Job No.
- B24LA04498
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - ADU ADDITION (800 SF) TO EXISITNG SFD WITH GARAGE PER 12.22 A33 C & E AND 65852.2, SEE COMMENTS
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- CofO Issued on 3/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | STARR CHEN |
| Corrections Issued | 4/2/2024 | STARR CHEN |
| Quality Review Completed | 4/3/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/23/2024 | STARR CHEN |
| Plan Check Approved | 11/13/2024 | STARR CHEN |
| Issued | 11/19/2024 | APPLICANT |
| CofO in Progress | 3/4/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 3/4/2026 | DEROLD HAUFF |
| CofO Issued | 3/4/2026 | DEROLD HAUFF |
| Permit Finaled | 3/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2024 | WALLIE JONG |
| Street Frontage | Cleared | 5/7/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | WALLIE JONG |
| Sewer availability | Cleared | 5/13/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 6/5/2024 | ERNEST TSE |
| Grading Pre-Inspection | Cleared | 7/16/2024 | RUSSELL BONVOULOIR |
| Supp. Use District POD/CDO/TDO | Cleared | 7/17/2024 | ANDREA MAGANA-WITHERS |
| Hydrant and Access approval | Cleared | 8/20/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 9/24/2024 | TREVOR QUAN |
| GPI Written Notices | Cleared | 11/13/2024 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Pre-Inspection | 4/4/2025 | Partial Inspection | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 4/14/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Underground Mechanical | 4/14/2025 | Approved | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 4/17/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Wood Frame | 7/18/2025 | Conditional Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| Gas Test | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 8/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 9/22/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 10/2/2025 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/2/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 1/29/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 1/29/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 1/29/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Smoke Detectors | 1/29/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/3/2026 | Approved | NICHOLAS LOPEZ |
| Final | 3/3/2026 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 3/3/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 3/3/2026 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 3/3/2026 | Not Required | NICHOLAS LOPEZ |
| Smoke Detectors | 3/3/2026 | Approved | NICHOLAS LOPEZ |