2811 1/2 S ALSACE AVE 90016

Certificate Information: 2811 1/2 S ALSACE AVE 90016

Application / Permit
24010-10000-00989
Plan Check / Job No.
B24LA04330
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 2 story detached accessory dwelling unit per ordinance.
Permit Issued
Issued on 1/26/2025
Issuing Office
Current Status
Issued on 1/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 FARSHAD ALIMOHAMADI
Corrections Issued 3/26/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 4/9/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 11/4/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 1/22/2025 FARSHAD ALIMOHAMADI
Issued 1/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/3/2024 DAVID LOPEZ
Construction near power lines Cleared 8/27/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/15/2024 DAVID LOPEZ
Sewer availability Cleared 10/15/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 1/7/2025 MITESH PATEL
Roof/Waste drainage to street Cleared 1/8/2025 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: NA67443       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 5/8/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 5/14/2025 Approved ARTHUR NEGRETE
Deputy Reinf. Concrete 5/21/2025 Conditional Approval ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 9/9/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 10/9/2025 Approved ARTHUR NEGRETE
HVAC-Rough 10/9/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 10/9/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 10/9/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 10/15/2025 Corrections Issued BRENDAN MORELLI
Green Building Rough 10/15/2025 Not Ready for Inspection BRENDAN MORELLI
Shower Pan 10/28/2025 Not Ready for Inspection DEVON JACKSON
Insulation 11/13/2025 Not Ready for Inspection DEVON JACKSON
Shower Pan 11/13/2025 Approved DEVON JACKSON
BUILDING-Rough-Frame 1/6/2026 Approved WILLIAM SIERRA
Green Building Rough 1/6/2026 Approved WILLIAM SIERRA
Insulation 1/6/2026 Corrections Issued WILLIAM SIERRA
Verify Sprinkler Sign Off 1/6/2026 Approved WILLIAM SIERRA
Insulation 1/27/2026 Approved GEM DE OCAMPO
Drywall Nailing 2/13/2026 Corrections Issued WILLIAM SIERRA
Drywall Nailing 2/18/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 5/4/2026 Approved BRENDAN MORELLI