1671 E IMPERIAL HWY 90059

Certificate Information: 1671 E IMPERIAL HWY 90059

Application / Permit
24010-10000-00947
Plan Check / Job No.
B24LA04175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2- 1-STORY ADU 800 SF WITH 2 CAR GARAGE 347 SF ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 4/1/2025
Issuing Office
Metro
Current Status
Issued on 4/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/7/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 SUNMIN LEE
Corrections Issued 3/9/2024 SUNMIN LEE
Quality Review Completed 3/15/2024 KEN GILL
Building Plans Picked Up 3/21/2024 APPLICANT
Applicant returned to address corrections 11/5/2024 SUNMIN LEE
Applicant returned to address corrections 12/26/2024 SUNMIN LEE
Plan Check Approved 1/16/2025 SUNMIN LEE
Issued 4/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/23/2024 CHRISTINA BRACO
Permit Cleared 4/23/2024 CHRISTINA BRACO
Hydrant and Access approval Cleared 5/17/2024 MATTHEW CRAIG
Low Impact Development (LID) Cleared 6/18/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/2/2024 CHRISTINA BRACO
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
Driveway location Cleared 9/25/2024 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 10/11/2024 CHRISTINA BRACO
Sewer availability Cleared 10/11/2024 CHRISTINA BRACO

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/27/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 5/30/2025 Partial Approval ANTHONY EGSON
Underground Mechanical 5/30/2025 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 6/25/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/30/2025 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 8/7/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/5/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Partial Approval ANTHONY EGSON
HVAC-Rough 11/5/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 11/5/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 11/6/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 11/6/2025 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 11/6/2025 Not Ready for Inspection ANTHONY EGSON
Wood Frame 11/6/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 11/26/2025 Approved ARTHUR NEGRETE
Green Building Rough 11/26/2025 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 11/26/2025 Approved ARTHUR NEGRETE
Wood Frame 11/26/2025 Approved ARTHUR NEGRETE
Insulation 12/4/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 12/4/2025 Approved ARTHUR NEGRETE
Drywall Nailing 12/18/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/15/2026 Approved ARTHUR NEGRETE
HVAC-Final 4/15/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 4/15/2026 Approved ARTHUR NEGRETE
Service/Power Release 4/15/2026 Approved ARTHUR NEGRETE
Sewer 4/15/2026 Approved ARTHUR NEGRETE