141 N PARKER ST 90731
Certificate Information: 141 N PARKER ST 90731
- Application / Permit
- 24010-10000-00930
- Plan Check / Job No.
- B24LA04062
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan BUILD 580 SQFT ACCESSORY DWELLING UNIT OVER AN EXISTING GARAGE. ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | JAD BASMA |
| Corrections Issued | 3/23/2024 | JAD BASMA |
| Quality Review Completed | 4/5/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/20/2024 | JAD BASMA |
| Applicant returned to address corrections | 10/2/2024 | JAD BASMA |
| Plan Check Approved | 11/5/2024 | JAD BASMA |
| Issued | 11/7/2024 | APPLICANT |
| CofO in Progress | 5/5/2026 | JOSEPH MCGARRY |
| Permit Finaled | 5/5/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/5/2026 | ANSON MAGLASANG |
| CofO Issued | 5/5/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2024 | ERIK BEASLEY |
| CPC | Cleared | 5/21/2024 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 8/20/2024 | JILVER MAZARIEGOS |
| Low Impact Development (LID) | Cleared | 8/30/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | JILVER MAZARIEGOS |
| GPI Written Notices | Cleared | 9/26/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 9/26/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/25/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/28/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/19/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/23/2025 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/23/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 8/18/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/12/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 9/12/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/16/2025 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/16/2025 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 9/16/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/16/2025 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 10/17/2025 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/17/2025 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/28/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/28/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/3/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 11/3/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/3/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/5/2025 | No Access for Inspection | ANTHONY EGSON |
| Drywall Nailing | 11/7/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | JOSEPH MCGARRY |
| Final | 2/18/2026 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/18/2026 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/18/2026 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/18/2026 | Approved | JOSEPH MCGARRY |
| Final | 3/25/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 3/25/2026 | Approved | JOSEPH MCGARRY |
| Final | 5/1/2026 | OK to Issue CofO | JOSEPH MCGARRY |