4044 E BEMIS ST 90039
Certificate Information: 4044 E BEMIS ST 90039
- Application / Permit
- 24010-10000-00909
- Plan Check / Job No.
- B24LA03981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Metro
- Current Status
- Issued on 11/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | KHEDER ALRAZAA |
| Corrections Issued | 3/27/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 3/29/2024 | KEN GILL |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Applicant returned to address corrections | 5/21/2024 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 6/6/2024 | KHEDER ALRAZAA |
| Plan Check Approved | 9/20/2024 | KHEDER ALRAZAA |
| Issued | 11/15/2024 | APPLICANT |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 5/23/2024 | DAVID URITA |
| Address approval | Cleared | 5/28/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 5/28/2024 | JESSICA OPINION |
| ZI | Cleared | 6/7/2024 | JACQUELINE TORRES |
| Hydrant and Access approval | Cleared | 6/14/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 9/10/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/10/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Buckley,, Jonathan Kaino; Lic. No.: S6407 | 5550 BALTIMORE DR. SUITE 100 LA MESA, CA 91942 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/3/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/6/2025 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Deputy Wood Construction | 3/21/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 6/17/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | REGINA MENDEZ |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 7/8/2025 | Approved | NICHOLAS LOPEZ |
| Sewer | 8/1/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/8/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Rough | 9/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/16/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/16/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 9/16/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 9/16/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/16/2025 | Approved | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 9/16/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 9/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/22/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 10/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/14/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Insulation | 10/27/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 11/10/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/16/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 12/16/2025 | Approved | GEM DE OCAMPO |