1601 N VISTA ST 90046
Certificate Information: 1601 N VISTA ST 90046
- Application / Permit
- 24010-10000-00897
- Plan Check / Job No.
- B24LA03894
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SINGLE FAMILY DWELLING PER LAMC 12.23A.5 RESTORATION OF DAMAGED NONCONFORMING BUILDING DUE TO FIRE AT FRONT OF LOT NFPA 13D COMPLY WITH DEPARTMENT ORDER effective date 07/21/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- Issued on 3/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | VIVIAN LAO |
| Corrections Issued | 3/11/2024 | VIVIAN LAO |
| Quality Review Completed | 3/13/2024 | GARO TELMI |
| Applicant returned to address corrections | 6/24/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 6/25/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 7/12/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 9/17/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 12/13/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 12/24/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 1/10/2025 | VIVIAN LAO |
| Plan Check Approved | 1/15/2025 | VIVIAN LAO |
| Plan Check Approved | 3/4/2025 | VIVIAN LAO |
| Issued | 3/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 5/17/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 7/11/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/15/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/16/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | JUSTIN BICOL |
| Work Adjacent to Public Way | Cleared | 8/27/2024 | JOSE RODRIGUEZ |
| HPOZ | Cleared | 12/6/2024 | JORGE RUIZ |
| Senate Bill 9 | Cleared | 12/6/2024 | JORGE RUIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | No Access for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 3/25/2025 | No Access for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/27/2025 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 3/27/2025 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 6/9/2025 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 6/9/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 6/20/2025 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/20/2025 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 6/20/2025 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 6/20/2025 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 6/20/2025 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/2/2025 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 7/2/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 7/2/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 7/2/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | ROY SPAULDING |
| Insulation | 7/24/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 7/24/2025 | Partial Approval | ROY SPAULDING |
| Interior/Exterior Lathing | 8/1/2025 | Approved | JOSH MEISTER |
| Shower Pan | 8/1/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 8/13/2025 | Not Ready for Inspection | ROY SPAULDING |
| Drywall Nailing | 8/14/2025 | Approved | ROY SPAULDING |
| Special/Order Compliance | 8/14/2025 | No Access for Inspection | RAUL BARAJAS |
| Pre-Inspection | 9/9/2025 | Not Ready for Inspection | ROY SPAULDING |
| Underground Mechanical | 12/2/2025 | Approved | ROY SPAULDING |
| Service/Power Release | 1/15/2026 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 1/22/2026 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 1/23/2026 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 2/13/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 2/13/2026 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Final | 3/18/2026 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 3/18/2026 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 4/3/2026 | Approved | DAVID WILLIAMS |
| Final | 4/3/2026 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/3/2026 | Approved | DAVID WILLIAMS |
| Green Building Final | 4/3/2026 | Approved | DAVID WILLIAMS |
| HVAC-Final | 4/3/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2026 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 4/3/2026 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 4/3/2026 | Approved | DAVID WILLIAMS |
| Grading Pre-Inspection | 4/10/2026 | No Access for Inspection | ROBERT PINA |
| Grading Pre-Inspection | 6/4/2026 | Not Ready for Inspection | ROY SPAULDING |