3414 1/2 W 27TH ST 90018
Certificate Information: 3414 1/2 W 27TH ST 90018
- Application / Permit
- 24010-10000-00860
- Plan Check / Job No.
- B24LA03809
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1-story ADU per LAMC 12.22A.33(c)(d) with attached trellis (218.25 sf), landscape, hardscape
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | KELVIN CHUONG |
| Corrections Issued | 3/11/2024 | KELVIN CHUONG |
| Building Plans Picked Up | 3/14/2024 | APPLICANT |
| Applicant returned to address corrections | 6/27/2024 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 9/6/2024 | SUNMIN LEE |
| Plan Check Approved | 9/13/2024 | SUNMIN LEE |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | JUSTIN HAWLEY |
| CofO in Progress | 1/14/2026 | JUSTIN HAWLEY |
| CofO in Progress | 1/14/2026 | JUSTIN HAWLEY |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
| CofO Issued | 1/14/2026 | DEROLD HAUFF |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | DAVID LOPEZ |
| HPOZ | Cleared | 6/27/2024 | DANIEL MATA |
| Sewer availability | Cleared | 6/27/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 8/19/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/19/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Arnold'S Construction Inc; Lic. No.: 1122609-B | 15216 NORDHOFF ST APT 102 NORTH HILLS, CA 91343 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 1545 VICTORY BLVD 2ND FLOOR N.C. HANSEN INC. GLENDALE, CA 91201 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2025 | Partial Approval | JOSE MACIAS |
| METHANE-Barrier | 4/11/2025 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 4/11/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/1/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 5/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 5/7/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Approved | WILLIAM SIERRA |
| Footing/Foundation/Slab | 5/7/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 5/7/2025 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Rough | 5/7/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 5/7/2025 | Approved | WILLIAM SIERRA |
| Underground Mechanical | 5/7/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 5/12/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/12/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/12/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 5/15/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 5/15/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/15/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 5/20/2025 | Approved | JOSE MACIAS |
| Pre-Inspection | 7/9/2025 | No Access for Inspection | JUSTIN HAWLEY |
| Final | 10/3/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 10/10/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Service/Power Release | 10/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 10/10/2025 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 10/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 1/6/2026 | No Access for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 1/13/2026 | Approved | JUSTIN HAWLEY |
| Final | 1/13/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Final | 1/13/2026 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 1/13/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 1/13/2026 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 1/13/2026 | Approved | JUSTIN HAWLEY |
| Final | 1/14/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 1/14/2026 | OK to Issue CofO | JUSTIN HAWLEY |