5030 N LINDLEY AVE 91316

Certificate Information: 5030 N LINDLEY AVE 91316

Application / Permit
24010-10000-00850
Plan Check / Job No.
B24LA03395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN NEW 1-STORY ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) SPRINKLERED NFPA13D THOUGH OUT
Permit Issued
Issued on 5/28/2024
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 JAD BASMA
Corrections Issued 3/2/2024 JAD BASMA
Quality Review Completed 3/5/2024 GARO TELMI
Applicant returned to address corrections 5/22/2024 JAD BASMA
Plan Check Approved 5/23/2024 JAD BASMA
Issued 5/28/2024 APPLICANT
CofO in Progress 7/29/2025 JOHN KIDWELL
Permit Finaled 8/18/2025 JOHN JANSON
CofO Issued 8/18/2025 JOHN JANSON
Permit Finaled 8/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 3/14/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/14/2024 EDGAR ALCARAZ
Construction near power lines Cleared 5/6/2024 ENRIQUE ACOSTA
Low Impact Development (LID) Cleared 5/6/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/6/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 5/7/2024 ADALBERTO VERA
Permit Cleared 5/10/2024 EDGAR ALCARAZ
GPI Written Notices Cleared 5/22/2024 JAD BASMA
Grading Pre-Inspection Cleared 5/22/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/4/2024 Approved JOHN KIDWELL
Underground Mechanical 9/4/2024 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 9/10/2024 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/12/2024 Conditional Approval JOHN KIDWELL
Footing/Foundation/Slab 9/12/2024 Conditional Approval JOHN KIDWELL
Deputy Reinf. Concrete 10/9/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 11/27/2024 Conditional Approval JOHN COLEMAN
HVAC-Rough 11/27/2024 Approved JOHN COLEMAN
PLUMBING-Rough 11/27/2024 Approved JOHN COLEMAN
Shower Pan 12/13/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/24/2024 Conditional Approval JOHN KIDWELL
Green Building Rough 12/24/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/24/2024 Partial Approval JOHN KIDWELL
Shower Pan 12/24/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/24/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/3/2025 Approved JOHN KIDWELL
Green Building Rough 1/3/2025 Approved JOHN KIDWELL
Insulation 1/3/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/3/2025 Partial Approval JOHN KIDWELL
Drywall Nailing 2/12/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 6/23/2025 Partial Inspection JOHN KIDWELL
Final 6/23/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 6/23/2025 Approved JOHN KIDWELL
Green Building Final 6/23/2025 Approved JOHN KIDWELL
HVAC-Final 6/23/2025 Partial Inspection JOHN KIDWELL
PLUMBING-Final 6/23/2025 Partial Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved JOHN KIDWELL
Service/Power Release 6/23/2025 Approved JOHN KIDWELL
Smoke Detectors 6/23/2025 Approved JOHN KIDWELL
Final 7/16/2025 OK to Issue CofO JOHN KIDWELL