4716 S 6TH AVE 90043

Certificate Information: 4716 S 6TH AVE 90043

Application / Permit
24010-10000-00840
Plan Check / Job No.
B24LA03763
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. PER ORDINANCE AT REAR OF LOT. CONST. PER W.F.P.P.
Permit Issued
Issued on 3/19/2024
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/4/2024 LAWRENCE QUIRANTE
Plans on Hold 3/4/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 3/7/2024 APPLICANT
Hold Released 3/15/2024 LAWRENCE QUIRANTE
Plan Check Approved 3/15/2024 JOSEPH RAFOLS
Issued 3/19/2024 APPLICANT
CofO in Progress 8/26/2024 ANTHONY EGSON
Permit Finaled 9/5/2024 RUBEN SALAS
CofO Issued 9/5/2024 RUBEN SALAS
Permit Finaled 9/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/6/2024 CHRISTINA BRACO
Hold Cleared 3/11/2024 ALEXIS SCHULTZ
Eng Process Fee Ord 176,300 Cleared 3/13/2024 CHRISTINA BRACO
Sewer availability Cleared 3/13/2024 CHRISTINA BRACO
Low Impact Development (LID) Cleared 3/14/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/14/2024 JUSTIN BICOL

Contact Information

Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2024 Corrections Issued ANTHONY EGSON
Pre-Inspection 4/23/2024 Partial Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/25/2024 Partial Approval SABAS ALONSO
Underground Mechanical 4/25/2024 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/1/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/1/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Approved ANTHONY EGSON
Underground Mechanical 5/20/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 5/21/2024 Approved ANTHONY EGSON
PLUMBING-Rough 5/21/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 5/22/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 5/22/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Partial Approval ANTHONY EGSON
Green Building Rough 5/22/2024 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 5/22/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 5/24/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/28/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 5/28/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 5/28/2024 Approved ANTHONY EGSON
Insulation 5/30/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 5/31/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 5/31/2024 Approved ANTHONY EGSON
Insulation 5/31/2024 Approved ANTHONY EGSON
Insulation 6/1/2024 Corrections Issued EUGENE CASSIDY
Drywall Nailing 6/3/2024 Approved ANTHONY EGSON
Drywall Nailing 6/4/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 6/4/2024 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 6/7/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/13/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 8/13/2024 Corrections Issued ANTHONY EGSON
Final 8/13/2024 Corrections Issued ANTHONY EGSON
Green Building Final 8/13/2024 Approved ANTHONY EGSON
Green Building Rough 8/13/2024 Approved ANTHONY EGSON
HVAC-Final 8/13/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 8/13/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved ANTHONY EGSON
Service/Power Release 8/13/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 8/13/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 8/16/2024 Not Ready for Inspection ANTHONY EGSON
Final 8/16/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 8/16/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 8/16/2024 Approved ANTHONY EGSON
Service/Power Release 8/16/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 8/16/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 8/19/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 8/19/2024 Approved ANTHONY EGSON
Final 8/20/2024 OK to Issue CofO ANTHONY EGSON
Service/Power Release 8/20/2024 Approved ANTHONY EGSON