2851 N SIERRA ST 90031

Certificate Information: 2851 N SIERRA ST 90031

Application / Permit
24010-10000-00837
Plan Check / Job No.
B24LA03745
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 1,200 SF DETACHED 2 STORY ADU WITH 278 SF FRONT PORCH ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/8/2024
Issuing Office
Current Status
Issued on 9/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 JAD BASMA
Corrections Issued 3/19/2024 JAD BASMA
Quality Review Completed 3/22/2024 GARO TELMI
Applicant returned to address corrections 8/13/2024 JAD BASMA
Applicant returned to address corrections 9/6/2024 JAD BASMA
Plan Check Approved 9/6/2024 JAD BASMA
Issued 9/8/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/11/2024 CHRISTINA BRACO
Street Frontage Cleared 4/11/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 4/17/2024 CHRISTINA BRACO
Sewer availability Cleared 4/17/2024 CHRISTINA BRACO
Disturb/Remove Protected Trees Cleared 5/31/2024 ADALBERTO VERA
"D" conditions Cleared 6/20/2024 JAZMIN ROQUE
"Q" conditions Cleared 6/20/2024 JAZMIN ROQUE
ZI Cleared 6/20/2024 JAZMIN ROQUE
Low Impact Development (LID) Cleared 7/25/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/30/2024 CHRISTINA BRACO
GPI Written Notices Cleared 8/12/2024 JAD BASMA
Grading Pre-Inspection Cleared 8/12/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2024 Partial Inspection OSVALDO PARAMO
Special/Order Compliance 9/16/2024 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 9/23/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 9/25/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/30/2024 Approved WILLIAM SIERRA
Special/Order Compliance 9/30/2024 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 11/4/2024 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 11/8/2024 Corrections Issued WILLIAM SIERRA
HVAC-Rough 11/8/2024 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 11/12/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/12/2024 Approved ALIZAH MAYAGOITIA
Wood Frame 11/14/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 11/19/2024 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved WILLIAM SIERRA
Green Building Rough 11/19/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 11/19/2024 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 11/19/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 11/20/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 11/21/2024 Approved ALIZAH MAYAGOITIA
Insulation 11/27/2024 Corrections Issued WILLIAM SIERRA
Drywall Nailing 12/9/2024 Approved ANTHONY RAMOS
Insulation 12/9/2024 Approved ANTHONY RAMOS
Sewer 12/17/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 12/17/2024 Approved ALIZAH MAYAGOITIA
Final 3/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/5/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 3/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 3/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 3/5/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 3/6/2025 Approved ALIZAH MAYAGOITIA