2310 E 7TH ST 90023

Certificate Information: 2310 E 7TH ST 90023

Application / Permit
24010-10000-00765
Plan Check / Job No.
B24LA03403
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(8) Auto Repair Garage
Work Description
**ePLAN** ** New pre-engineered metal building for office and maintenance facilities (auto repair) for City of L.A.. Replace portions of adjacent pavement and construct two new storm water basins.
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
Issued on 1/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 JOHNNY WU
Assigned to Zoning Architect 3/14/2024 JOHNNY WU
Corrections Issued 4/4/2024 JOHNNY WU
Quality Review Completed 4/9/2024 RODOLFO ARIAS
Applicant returned to address corrections 4/26/2024 JOHNNY WU
Applicant returned to address corrections 5/29/2024 JOHNNY WU
Applicant returned to address corrections 6/3/2024 JOHNNY WU
Applicant returned to address corrections 6/20/2024 JOHNNY WU
Applicant returned to address corrections 7/19/2024 JOHNNY WU
Applicant returned to address corrections 7/23/2024 JOHNNY WU
Applicant returned to address corrections 12/2/2024 JOHNNY WU
Applicant returned to address corrections 12/11/2024 JOHNNY WU
Applicant returned to address corrections 12/17/2024 JOHNNY WU
Applicant returned to address corrections 1/22/2025 JOHNNY WU
Plan Check Approved 1/23/2025 JOHNNY WU
No Progress 1/23/2025 JOHNNY WU
Plan Check Approved 1/23/2025 JOHNNY WU
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 5/21/2024 YINGSHI HUANG
Automotive Use Cleared 5/31/2024 NOAH MCCOY
Automotive Use Cleared 5/31/2024 NOAH MCCOY
Clean Up Green Up Cleared 5/31/2024 NOAH MCCOY
ZI Cleared 5/31/2024 NOAH MCCOY
ZI Cleared 5/31/2024 NOAH MCCOY
City owned building/parcel Cleared 6/3/2024 JOHNNY WU
Historic Resource Verification Cleared 6/4/2024 RAFAEL FONTES
Redevelopment Project Area Cleared 6/6/2024 YASMINE BASHIRI
ZI Cleared 6/6/2024 YASMINE BASHIRI
Eng Process Fee Ord 176,300 Cleared 6/13/2024 JUSTIN BICOL
Sewer availability Cleared 6/13/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 6/25/2024 RUEL COLE
Body shop Cleared 7/18/2024 SCAQMD APPROVED
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
DAS Clearance Cleared 10/18/2024 Jesse Arellano
Green Code Cleared 10/25/2024 Jesse Arellano
Low Impact Development (LID) Cleared 11/13/2024 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/20/2024 JUSTIN BICOL
Address approval Cleared 11/21/2024 CELINA MORENO
Highway dedication Cleared 12/12/2024 TREVOR QUAN
Permit Cleared 1/6/2025 CELINA MORENO
Zoning Plan Check Cleared 1/22/2025 Jesse Arellano
Miscellaneous Cleared 1/23/2025 JOHNNY WU

Contact Information

Architect Kristedja,, John Mark; Lic. No.: NA22297       ,
Contractor Efs West; Lic. No.: 826003-B       ,
Contractor Golden Aquisition Corporation; Lic. No.: 826003-B       ,
Engineer Brown,, Emily; Lic. No.: NA5390       ,
Engineer Carter,, Ryan; Lic. No.: C72087 2250 DOUGALS BLVD #200      ROSEVILLE, CA 95661

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/4/2025 Conditional Approval LARRY ARNICK
Deputy Grading 2/21/2025 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 2/21/2025 Conditional Approval LARRY ARNICK
Piling/Pier/Caisson 2/21/2025 Partial Inspection LARRY ARNICK
Deputy Grading 2/28/2025 Conditional Approval LARRY ARNICK
Piling/Pier/Caisson 3/20/2025 Partial Inspection LARRY ARNICK
Deputy Grading 3/24/2025 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/24/2025 Conditional Approval LARRY ARNICK
Deputy Grading 3/25/2025 Conditional Approval LARRY ARNICK
Deputy Grading 3/26/2025 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/26/2025 Conditional Approval LARRY ARNICK
Deputy Grading 3/28/2025 Conditional Approval LARRY ARNICK
Deputy Grading 4/1/2025 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 4/1/2025 Conditional Approval LARRY ARNICK
Deputy Grading 4/2/2025 Conditional Approval LARRY ARNICK
Deputy Grading 4/3/2025 Conditional Approval LARRY ARNICK
Deputy Grading 4/4/2025 Conditional Approval LARRY ARNICK
Pre-Inspection 4/15/2025 Conditional Approval LARRY ARNICK
Piling/Pier/Caisson 4/24/2025 Partial Inspection LARRY ARNICK
Piling/Pier/Caisson 4/29/2025 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/14/2025 Approved LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Corrections Issued LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 1/29/2026 Partial Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/5/2026 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 5/14/2026 Partial Approval RONALD JIMENEZ
Drywall Nailing 5/20/2026 Partial Approval RONALD JIMENEZ