13226 W MORRISON ST 91423

Certificate Information: 13226 W MORRISON ST 91423

Application / Permit
24010-10000-00755
Plan Check / Job No.
B24LA03371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: New 2 story SFD with attached garage and attached ADU per LAMC 12.22.A.33(c) and (e)
Permit Issued
Issued on 5/30/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 ARSALAN SHABESTARI
Corrections Issued 3/14/2024 ARSALAN SHABESTARI
Quality Review Completed 3/15/2024 YOUNG KIM
Applicant returned to address corrections 3/20/2024 YOUNG KIM
Plan Check Approved 5/28/2024 ARSALAN SHABESTARI
Issued 5/30/2024 APPLICANT
CofO in Progress 2/7/2025 OGANES TARAKHCHYAN
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/21/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/21/2024 LEE GUILBEAUX
Permit Cleared 3/21/2024 LEE GUILBEAUX
Sewer availability Cleared 3/21/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/21/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 3/26/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/26/2024 LEE GUILBEAUX
Trees in Parkway Cleared 4/5/2024 ADALBERTO VERA
Miscellaneous Cleared 4/9/2024 MATHEW QUAN
ZA Case Cleared 4/9/2024 MATHEW QUAN
ZA Case Cleared 4/9/2024 MATHEW QUAN
Construction near power lines Cleared 5/8/2024 RIDWAN HARDY
Construction within easement Cleared 5/8/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 5/13/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/4/2024 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 6/4/2024 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 6/6/2024 Approved JOSE AVILA
Footing/Foundation/Slab 6/6/2024 Partial Approval JOSE AVILA
Pre-Inspection 6/6/2024 Off-Hour Fees Due
Pre-Inspection 6/7/2024 Off-Hour Fees Due
Deputy Reinf. Concrete 6/10/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/10/2024 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 6/12/2024 Approved JOHN COLEMAN
Deputy Reinf. Concrete 6/13/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval SALVADOR MARTINEZ
HVAC-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/31/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/31/2024 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 8/6/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 8/6/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved OGANES TARAKHCHYAN
Shower Pan 8/6/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 8/6/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/8/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 8/12/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 8/12/2024 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/12/2024 Approved OGANES TARAKHCHYAN
Insulation 8/14/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/14/2024 Partial Approval VINCENT HANLEY
Insulation 8/15/2024 Approved VINCENT HANLEY
Deputy Steel/Welding 8/19/2024 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 8/19/2024 Approved ALEXANDER HANDY
HVAC-Final 11/4/2024 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 11/6/2024 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Final 11/14/2024 Approved GAREN HAYRAPETYAN
Sewer 11/18/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 12/4/2024 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Final 12/4/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 12/9/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/16/2024 Approved OGANES TARAKHCHYAN
Final 12/16/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/16/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 12/16/2024 Approved OGANES TARAKHCHYAN
Final 12/23/2024 Corrections Issued RYAN SALAZAR
Green Building Final 12/23/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Required RYAN SALAZAR
Service/Power Release 12/23/2024 Not Ready for Inspection RYAN SALAZAR
Final 2/6/2025 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 2/6/2025 Approved OGANES TARAKHCHYAN