922 N MCFARLAND AVE 90744

Certificate Information: 922 N MCFARLAND AVE 90744

Application / Permit
24010-10000-00739
Plan Check / Job No.
B24LA03280
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
40'-0" X 27'-10" NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
Permit Issued
Issued on 6/13/2024
Issuing Office
Current Status
CofO Issued on 6/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/1/2024 DANIEL ABRAMYAN
Corrections Issued 3/2/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 4/12/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 6/5/2024 DANIEL ABRAMYAN
Plan Check Approved 6/11/2024 DANIEL ABRAMYAN
Issued 6/13/2024 APPLICANT
CofO in Progress 6/6/2025 EUGENE CASSIDY
Permit Finaled 6/9/2025 ANSON MAGLASANG
CofO Issued 6/9/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/28/2024 JILVER MAZARIEGOS
Clean Up Green Up Cleared 3/28/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 4/8/2024 JILVER MAZARIEGOS
Sewer availability Cleared 4/8/2024 JILVER MAZARIEGOS
Low Impact Development (LID) Cleared 5/30/2024 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/4/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2024 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 6/27/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 6/27/2024 Approved EUGENE CASSIDY
Footing/Foundation/Slab 7/18/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/1/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 8/1/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/1/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/1/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/23/2024 No Access for Inspection EUGENE CASSIDY
Green Building Rough 8/23/2024 No Access for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 8/23/2024 No Access for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/4/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 9/4/2024 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 9/4/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/11/2024 Approved JOSEPH MCGARRY
Green Building Rough 9/11/2024 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 9/11/2024 Approved JOSEPH MCGARRY
Insulation 9/19/2024 Corrections Issued JOSEPH MCGARRY
Insulation 9/23/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/30/2024 Partial Approval EUGENE CASSIDY
Shower Pan 11/19/2024 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 11/25/2024 Approved JOSEPH MCGARRY
Shower Pan 11/25/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 2/3/2025 Corrections Issued EUGENE CASSIDY
Underground Mechanical 2/4/2025 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/24/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/6/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 3/11/2025 Approved JOSEPH MCGARRY
HVAC-Final 3/18/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 3/19/2025 Approved EUGENE CASSIDY
Gas Test 3/19/2025 Approved EUGENE CASSIDY
HVAC-Final 3/19/2025 Approved EUGENE CASSIDY
Drywall Nailing 5/1/2025 Not Ready for Inspection JOHN KLARIN
Final 5/1/2025 Not Ready for Inspection JOHN KLARIN
Green Building Final 5/1/2025 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready JOHN KLARIN
Service/Power Release 5/1/2025 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 5/1/2025 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 5/2/2025 Corrections Issued JOHN KLARIN
Final 5/8/2025 Corrections Issued EUGENE CASSIDY
Drywall Nailing 6/4/2025 Approved EUGENE CASSIDY
Final 6/4/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 6/4/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/4/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/4/2025 Approved EUGENE CASSIDY
Final 6/6/2025 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 6/6/2025 Approved EUGENE CASSIDY