14820 W CALIFA ST 91411
Certificate Information: 14820 W CALIFA ST 91411
- Application / Permit
- 24010-10000-00700
- Plan Check / Job No.
- B24LA03135
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2 story detached ADU with attached 2-car garage. PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | CARLOS MONTES |
| Corrections Issued | 3/15/2024 | CARLOS MONTES |
| Quality Review Completed | 3/19/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/21/2025 | CARLOS MONTES |
| Plan Check Approved | 5/14/2025 | CARLOS MONTES |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 3/14/2026 | VINCENT HANLEY |
| Permit Finaled | 3/18/2026 | RICHARD STEINBACH |
| CofO Issued | 3/18/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/18/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/20/2024 | RIDWAN HARDY |
| Address approval | Cleared | 1/12/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/14/2025 | RYAN CASTRO |
| Trees in Parkway | Cleared | 2/11/2025 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 3/27/2025 | ERNEST TSE |
| Permit | Cleared | 4/3/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 4/3/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mnatsakanyan,, Arthur; Lic. No.: C74802 | 4730 WOODMAN AVE STE 360 SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/16/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 7/16/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Partial Approval | LOUIS ESCOTO |
| Sewer | 7/18/2025 | Corrections Issued | LOUIS ESCOTO |
| Underground Mechanical | 7/18/2025 | Corrections Issued | LOUIS ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 9/15/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/16/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/16/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/16/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/16/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 9/16/2025 | Approved | RYAN SALAZAR |
| Insulation | 9/26/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/26/2025 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 9/26/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/1/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 10/22/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/28/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/21/2026 | Approved | RYAN SALAZAR |
| Final | 1/21/2026 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 1/21/2026 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 1/21/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 1/21/2026 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/21/2026 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/13/2026 | Approved | VINCENT HANLEY |
| Final | 3/13/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/13/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/13/2026 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/13/2026 | Approved | VINCENT HANLEY |