5109 S 11TH AVE 90043

Certificate Information: 5109 S 11TH AVE 90043

Application / Permit
24010-10000-00692
Plan Check / Job No.
B24LA03083
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) 1-STORY DETACHED ADU. NEW ADU PER LAMC 12.22 A.33 (c)-(d). 1 OF 3
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
Issued on 6/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/21/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 ADRIANA LOPEZ
Corrections Issued 4/2/2024 ADRIANA LOPEZ
Quality Review Completed 4/9/2024 YOUNG KIM
Applicant returned to address corrections 12/4/2024 ADRIANA LOPEZ
Applicant returned to address corrections 3/10/2025 ADRIANA LOPEZ
Applicant returned to address corrections 4/17/2025 ADRIANA LOPEZ
Plan Check Approved 6/11/2025 ADRIANA LOPEZ
Issued 6/25/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/3/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/7/2024 JEANIE LAM
Sewer availability Cleared 10/7/2024 JEANIE LAM
Low Impact Development (LID) Cleared 3/26/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 3/31/2025 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/27/2025 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 9/3/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 9/3/2025 Approved LUIS CASTRO
PLUMBING-Rough 9/3/2025 Not Ready for Inspection LUIS CASTRO
Sewer 9/3/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 9/24/2025 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 9/24/2025 Partial Approval BRENDAN MORELLI
Insulation 9/26/2025 Partial Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/12/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 11/12/2025 Corrections Issued LUIS CASTRO
Green Building Rough 11/12/2025 Approved LUIS CASTRO
HVAC-Rough 11/12/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 11/12/2025 Corrections Issued LUIS CASTRO
Verify Sprinkler Sign Off 11/12/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/3/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 12/3/2025 Approved LUIS CASTRO
HVAC-Rough 12/3/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 12/3/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 12/3/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/8/2025 Approved LUIS CASTRO
Insulation 1/7/2026 Partial Approval LUIS CASTRO
Drywall Nailing 1/27/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 2/5/2026 Approved LUIS CASTRO
Underground Mechanical 3/26/2026 Approved LUIS CASTRO
Sewer 4/7/2026 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Final 5/13/2026 Approved LUIS CASTRO
Final 5/13/2026 Corrections Issued LUIS CASTRO
Green Building Final 5/13/2026 Approved LUIS CASTRO
PLUMBING-Final 5/13/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Required LUIS CASTRO
Service/Power Release 5/13/2026 Not Ready for Inspection LUIS CASTRO
Smoke Detectors 5/13/2026 Approved LUIS CASTRO