13468 W HERRON ST 91342

Certificate Information: 13468 W HERRON ST 91342

Application / Permit
24010-10000-00684
Plan Check / Job No.
B24LA03059
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU (915 SQFT) WITH ATTACHED COVERED PATIO (67 SQFT) PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
Permit Issued
Issued on 8/1/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 ZAW HAN
Corrections Issued 2/26/2024 ZAW HAN
Building Plans Picked Up 2/27/2024 APPLICANT
Plan Check Approved 3/28/2024 DANIEL SMILEY
Issued 8/1/2024 APPLICANT
CofO in Progress 12/23/2024 KEVIN BERBERYAN
Permit Finaled 1/2/2025 RUBEN SALAS
CofO Issued 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/1/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 3/5/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/5/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/27/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/27/2024 EDGAR ALCARAZ

Contact Information

Contractor Ficrest Construction Inc; Lic. No.: 898747-B 4104 BRIGGS AVE      MONTROSE, CA 91020

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2024 Partial Inspection KEVIN BERBERYAN
Underground Mechanical 8/16/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 8/20/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 9/6/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/6/2024 Partial Approval KEVIN BERBERYAN
Underground Mechanical 9/6/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/13/2024 Approved JACK KARGODORIAN
Underground Mechanical 9/13/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/17/2024 Approved KEVIN BERBERYAN
Wood Frame 9/17/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 9/18/2024 Approved KEVIN BERBERYAN
Green Building Rough 9/18/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 9/18/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/18/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 9/26/2024 Approved KEVIN BERBERYAN
Shower Pan 9/26/2024 Approved KEVIN BERBERYAN
Insulation 9/30/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 9/30/2024 Partial Approval KEVIN BERBERYAN
Drywall Nailing 10/3/2024 Approved KEVIN BERBERYAN
Green Building Rough 10/3/2024 Approved KEVIN BERBERYAN
Insulation 11/15/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 11/15/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 11/19/2024 Partial Approval KEVIN BERBERYAN
HVAC-Final 11/19/2024 Approved KEVIN BERBERYAN
Service/Power Release 11/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 12/2/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 12/2/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 12/2/2024 Approved KEVIN BERBERYAN
Smoke Detectors 12/2/2024 Approved KEVIN BERBERYAN