5718 S 7TH AVE 90043
Certificate Information: 5718 S 7TH AVE 90043
- Application / Permit
- 24010-10000-00670
- Plan Check / Job No.
- B24LA02969
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New two story detached ADU per LAMC 12.22A.33 (c) and (d)
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 3/12/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 3/14/2024 | TU HUA |
| Applicant returned to address corrections | 5/23/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 7/10/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 8/13/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 12/24/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/3/2025 | MARCELA FRANQUEZ |
| Issued | 1/3/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | LUIS CASTRO |
| CofO Issued | 3/12/2026 | DEROLD HAUFF |
| Permit Finaled | 3/12/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/4/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 5/10/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 12/5/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/26/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 3/20/2025 | Approved | LUIS CASTRO |
| Deputy Reinf. Concrete | 3/21/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Partial Inspection | LUIS CASTRO |
| Green Building Rough | 4/7/2025 | Not Ready for Inspection | LUIS CASTRO |
| Verify Sprinkler Sign Off | 4/7/2025 | Not Ready for Inspection | LUIS CASTRO |
| Deputy Wood Construction | 4/23/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Approved | LUIS CASTRO |
| Wood Frame | 4/29/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 5/6/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 5/6/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 5/6/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/8/2025 | Conditional Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 5/8/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 5/8/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 5/8/2025 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 5/8/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/15/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 5/20/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 6/2/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 6/2/2025 | Approved | LUIS CASTRO |
| Shower Pan | 6/9/2025 | Partial Approval | LUIS CASTRO |
| Shower Pan | 6/13/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 6/18/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 7/29/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 7/29/2025 | Not Ready for Inspection | LUIS CASTRO |
| Sewer | 7/29/2025 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 7/29/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 7/31/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 8/4/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 8/4/2025 | Corrections Issued | LUIS CASTRO |
| Sewer | 8/5/2025 | Approved | LUIS CASTRO |
| Special/Order Compliance | 8/5/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 8/6/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 8/6/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/3/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 9/10/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/8/2025 | Corrections Issued | LUIS CASTRO |
| Final | 10/8/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 10/8/2025 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 10/8/2025 | Not Ready for Inspection | LUIS CASTRO |
| Smoke Detectors | 10/8/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/19/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 11/19/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 11/19/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 11/19/2025 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 12/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 12/9/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 12/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 3/4/2026 | Approved | LUIS CASTRO |
| Final | 3/4/2026 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 3/4/2026 | Approved | LUIS CASTRO |