4425 1/2 W 63RD ST 90043

Certificate Information: 4425 1/2 W 63RD ST 90043

Application / Permit
24010-10000-00669
Plan Check / Job No.
B24LA02968
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Detached garage conversion to ADU
Permit Issued
Issued on 7/25/2024
Issuing Office
Current Status
Issued on 7/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/20/2024 APPLICANT
Assigned to Plan Check Engineer 2/23/2024 NEHEMIAS RAMOS
Corrections Issued 2/24/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 7/16/2024 NEHEMIAS RAMOS
Plan Check Approved 7/24/2024 DANIEL SANJUAN
Issued 7/25/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/26/2024 WALLIE JONG
Sewer availability Cleared 2/26/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/27/2024 WALLIE JONG
Construction near power lines Cleared 7/7/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 7/17/2024 MICHAEL TEMPLE

Contact Information

Contractor Kvm Homes Llc; Lic. No.: 911466-B       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/27/2026 Partial Inspection RAUL BARAJAS
Underground Mechanical 5/27/2026 Approved RAUL BARAJAS