3598 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3598 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 24010-10000-00643
- Plan Check / Job No.
- B24LA02899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE + ROOF DECK. FIRE SPRINKLER REQUIRED.
- Permit Issued
- Issued on 8/14/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | WEIJIAN HUANG |
| Corrections Issued | 2/28/2024 | WEIJIAN HUANG |
| Quality Review Completed | 3/6/2024 | DANIEL CHAN |
| Building Plans Picked Up | 3/7/2024 | APPLICANT |
| Applicant returned to address corrections | 5/1/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 7/18/2024 | WEIJIAN HUANG |
| Plan Check Approved | 8/13/2024 | WEIJIAN HUANG |
| Issued | 8/14/2024 | APPLICANT |
| CofO in Progress | 9/7/2025 | KIRK SANDERS |
| Permit Finaled | 9/16/2025 | RICHARD STEINBACH |
| CofO Issued | 9/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2024 | VLADIMIR ARUTYUNYAN |
| ZA Case | Cleared | 3/12/2024 | MATHEW QUAN |
| Trees in Parkway | Cleared | 4/4/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 4/8/2024 | TOMMY YIN |
| Hydrant and Access approval | Cleared | 4/12/2024 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | DARIN LAM |
| Permit | Cleared | 5/13/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 5/13/2024 | DARIN LAM |
| Sewer availability | Cleared | 5/13/2024 | DARIN LAM |
| Construction near power lines | Cleared | 6/5/2024 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 7/18/2024 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 7/18/2024 | MATTHEW JENKINS |
| Specific Plan | Cleared | 8/8/2024 | JOSHUA JONES |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Consulting Llc; Lic. No.: 942979-B | 9055 ALCOTT STREET UNIT 1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2024 | Corrections Issued | DANIEL VERA |
| Special/Order Compliance | 9/12/2024 | Partial Inspection | KENNETH NAGLE |
| Special/Order Compliance | 9/12/2024 | Partial Inspection | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Partial Approval | DANIEL VERA |
| Underground Mechanical | 10/4/2024 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 10/9/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | DANIEL VERA |
| Deputy Wood Construction | 1/9/2025 | Conditional Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/23/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 1/28/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 1/28/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/14/2025 | Conditional Approval | DANIEL VERA |
| Green Building Rough | 2/14/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 2/14/2025 | Approved | DANIEL VERA |
| Insulation | 2/19/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 2/24/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 2/25/2025 | Approved | DANIEL VERA |
| Shower Pan | 2/25/2025 | Approved | DANIEL VERA |
| HVAC-Final | 7/29/2025 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 8/15/2025 | Approved | BOBBY KEY |
| HVAC-Final | 8/15/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 8/28/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 9/2/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/2/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | KIRK SANDERS |
| Final | 9/5/2025 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 9/5/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/5/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 9/5/2025 | Approved | KIRK SANDERS |
| Smoke Detectors | 9/5/2025 | Approved | KIRK SANDERS |