1158 W 1ST ST 90731

Certificate Information: 1158 W 1ST ST 90731

Application / Permit
24010-10000-00611
Plan Check / Job No.
B24LA02817
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED ACCESSORY DWELLING UNIT W/ ROOF DECK PER LAMC 12.22 A.33 (c)-(d) (1-STORY)
Permit Issued
Issued on 10/7/2024
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 CARLOS MONTES
Corrections Issued 2/20/2024 CARLOS MONTES
Quality Review Completed 2/23/2024 KEN GILL
Building Plans Picked Up 2/26/2024 APPLICANT
Applicant returned to address corrections 4/17/2024 CARLOS MONTES
Applicant returned to address corrections 5/7/2024 CARLOS MONTES
Plan Check Approved 9/18/2024 CARLOS MONTES
Issued 10/7/2024 APPLICANT
CofO in Progress 8/15/2025 ANTHONY EGSON
Permit Finaled 8/18/2025 ANSON MAGLASANG
CofO Issued 8/18/2025 ANSON MAGLASANG
Permit Finaled 8/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

ZA Case Cleared 2/26/2024 JASON CHAN
ZA Case Cleared 2/26/2024 JASON CHAN
ZA Case Cleared 2/26/2024 JASON CHAN
Address approval Cleared 5/14/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 5/14/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 5/14/2024 JILVER MAZARIEGOS
Permit Cleared 5/15/2024 JILVER MAZARIEGOS
Low Impact Development (LID) Cleared 7/26/2024 ERNEST TSE
GPI Written Notices Cleared 8/1/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 8/1/2024 CARLOS MONTES
Sewer availability Cleared 8/7/2024 JILVER MAZARIEGOS
Trees in Parkway Cleared 9/6/2024 ADALBERTO VERA

Contact Information

Contractor Tonthat Constructions; Lic. No.: 932770-B 1536 W LASTER AVE      ANAHEIM, CA 92802

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 11/8/2024 Partial Approval JOSEPH MCGARRY
Underground Mechanical 11/8/2024 Corrections Issued JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 11/27/2024 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 1/21/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 1/21/2025 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Approved JOSEPH MCGARRY
Green Building Rough 1/21/2025 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 1/21/2025 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 1/21/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 2/6/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/6/2025 Approved JOSEPH MCGARRY
Green Building Rough 2/6/2025 Approved JOSEPH MCGARRY
HVAC-Rough 2/6/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/6/2025 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 2/6/2025 Approved JOSEPH MCGARRY
Shower Pan 2/7/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/11/2025 Approved JOSEPH MCGARRY
Insulation 2/20/2025 Approved JOSEPH MCGARRY
Drywall Nailing 2/25/2025 Approved JOSEPH MCGARRY
Pre-Inspection 3/25/2025 Approved JOSEPH MCGARRY
Special/Order Compliance 3/25/2025 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 4/7/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 4/7/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 4/7/2025 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 4/7/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 4/7/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 4/30/2025 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 4/30/2025 Approved JOSEPH MCGARRY
Final 4/30/2025 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 4/30/2025 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 4/30/2025 Approved JOSEPH MCGARRY
HVAC-Final 4/30/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 4/30/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Required JOSEPH MCGARRY
Service/Power Release 4/30/2025 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 4/30/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/26/2025 Approved JOSEPH MCGARRY
Final 6/26/2025 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 6/26/2025 Approved JOSEPH MCGARRY
Service/Power Release 6/26/2025 Not Ready for Inspection JOSEPH MCGARRY
Final 8/14/2025 OK to Issue CofO ANTHONY EGSON
Service/Power Release 8/14/2025 Approved ANTHONY EGSON