5115 E CORINGA DR 90042

Certificate Information: 5115 E CORINGA DR 90042

Application / Permit
24010-10000-00603
Plan Check / Job No.
B24LA02783
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New detached A.D.U. per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2024 APPLICANT
Assigned to Plan Check Engineer 2/21/2024 CAROLEAN BASMA
Corrections Issued 2/22/2024 CAROLEAN BASMA
Applicant returned to address corrections 4/3/2024 CAROLEAN BASMA
Plan Check Approved 4/11/2024 CAROLEAN BASMA
Issued 4/15/2024 APPLICANT
CofO in Progress 9/9/2024 ROY SPAULDING
CofO in Progress 9/11/2024 ROY SPAULDING
Permit Finaled 9/17/2024 DEROLD HAUFF
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/22/2024 CAROLEAN BASMA
Address approval Cleared 2/27/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/28/2024 JUSTIN BICOL
Sewer availability Cleared 2/28/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 3/14/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 3/14/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 3/14/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 3/14/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 3/14/2024 JUSTIN BICOL
Low Impact Development (LID) Cleared 3/14/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/14/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2024 Not Ready for Inspection CRAIG VAUGHAN
Underground Mechanical 4/19/2024 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/22/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/22/2024 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/20/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/20/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 5/20/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/20/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/20/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/20/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 5/22/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 5/22/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/22/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/24/2024 Approved CRAIG VAUGHAN
Insulation 5/29/2024 Approved CRAIG VAUGHAN
Drywall Nailing 5/31/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/18/2024 Approved CRAIG VAUGHAN
Shower Pan 6/18/2024 Approved CRAIG VAUGHAN
Sewer 7/9/2024 Approved CRAIG VAUGHAN
Underground Mechanical 7/9/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Final 8/30/2024 Approved CRAIG VAUGHAN
Final 8/30/2024 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 8/30/2024 Approved CRAIG VAUGHAN
Final 9/5/2024 OK to Issue CofO ROY SPAULDING
Service/Power Release 9/5/2024 Approved ROY SPAULDING
Final 9/10/2024 OK to Issue CofO ROY SPAULDING