1532 S HI POINT ST 90035
Certificate Information: 1532 S HI POINT ST 90035
- Application / Permit
- 24010-10000-00599
- Plan Check / Job No.
- B24LA02758
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- *eplan* NEW 5 STORY TYPE IIIA 50 UNITS (39 LI + 10 MI+1 MNGR) AFFORDABLE HOUSING APARTMENT, USING 12.22.A.25/AB1763/AB2345 INCENTIVES
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- Issued on 5/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | KEVIN MORALES |
| Assigned to Zoning Architect | 2/15/2024 | LY CHEA |
| Corrections Issued | 2/22/2024 | KEVIN MORALES |
| Quality Review Completed | 2/26/2024 | EUGENE BARBEAU |
| Plan Check Approved | 1/15/2025 | KEVIN MORALES |
| Issued | 5/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2024 | WALLIE JONG |
| Highway dedication | Cleared | 2/26/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/26/2024 | JEANIE LAM |
| Building over 36-ft | Cleared | 5/14/2024 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 5/22/2024 | JOHN CONNEALLY |
| Green Code | Cleared | 5/29/2024 | KEVIN MORALES |
| Fire Marshal Fire Life Safety | Cleared | 6/4/2024 | MENOA AGHAJANI |
| Low Impact Development (LID) | Cleared | 6/7/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | JEANIE LAM |
| Density Bonus | Cleared | 9/24/2024 | OLIVIA JIN |
| SB8 RUD | Cleared | 9/24/2024 | OLIVIA JIN |
| "Q" conditions | Cleared | 10/15/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 10/15/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 10/15/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 10/15/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 10/15/2024 | YINGSHI HUANG |
| Opn space landscape/Water mgmt | Cleared | 10/15/2024 | YINGSHI HUANG |
| Frnt yard landscape/Water mgmt | Cleared | 10/17/2024 | YINGSHI HUANG |
| DAS Clearance | Cleared | 11/6/2024 | KEVIN MORALES |
| Miscellaneous | Cleared | 12/3/2024 | YINGSHI HUANG |
| Zoning Plan Check | Cleared | 12/13/2024 | Rodolfo Arias |
Contact Information
| Architect | Holtz,, Donald Lee; Lic. No.: C21677 | 700 S FLOWER ST #1000 LOS ANGELES, CA 90017 |
| Contractor | H T A Construction & Development; Lic. No.: 1044038-B | , |
| Contractor | Hta Construction & Development; Lic. No.: 1044038-B | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
| Engineer | Jahani,, Fereidoun; Lic. No.: C62875 | 3720 BLANCHE ST PASADENA, CA 91107 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/23/2025 | Partial Approval | RAFAEL CORTES |
| METHANE-Barrier | 7/23/2025 | Partial Approval | RAFAEL CORTES |
| METHANE-Subgrade | 7/23/2025 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 7/24/2025 | No Access for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Barrier | 9/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Subgrade | 9/3/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/4/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 10/14/2025 | Conditional Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 11/3/2025 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 11/26/2025 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 12/10/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 12/12/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 12/15/2025 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 12/17/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 12/17/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 12/18/2025 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 12/22/2025 | No Access for Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 1/9/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 1/13/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 1/14/2026 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 1/16/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Deputy Steel/Welding | 1/20/2026 | Conditional Approval | OSVALDO PARAMO |
| Wood Frame | 1/21/2026 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 1/23/2026 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 1/27/2026 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 1/28/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 2/2/2026 | No Access for Inspection | RAFAEL CORTES |
| Pre-Inspection | 2/4/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 2/5/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 2/6/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 2/9/2026 | Partial Inspection | RAFAEL CORTES |
| Pre-Inspection | 2/11/2026 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 2/12/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/18/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 2/20/2026 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 2/24/2026 | Conditional Approval | RAFAEL CORTES |
| Drywall Nailing | 2/24/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 2/26/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 2/27/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 3/2/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/6/2026 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 3/10/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 3/11/2026 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 3/16/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 3/17/2026 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 3/18/2026 | Approved | RAFAEL CORTES |
| Light Gage Steel Frame | 3/24/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 3/24/2026 | Corrections Issued | RAFAEL CORTES |
| Insulation | 3/27/2026 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 4/1/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Wall Anchors | 4/23/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 4/27/2026 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 4/27/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 4/28/2026 | No Access for Inspection | RAFAEL CORTES |
| METHANE-Rough | 4/28/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 4/28/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 4/28/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 4/30/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 5/1/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 5/4/2026 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 5/6/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 5/11/2026 | Partial Approval | RAFAEL CORTES |
| Wall Anchors | 5/18/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 5/20/2026 | No Access for Inspection | RAFAEL CORTES |
| Drywall Nailing | 5/26/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 6/1/2026 | No Access for Inspection | RAFAEL CORTES |
| Insulation | 6/2/2026 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 6/5/2026 | No Access for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 6/8/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 6/9/2026 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 6/10/2026 | No Access for Inspection | RAFAEL CORTES |
| Drywall Nailing | 6/23/2026 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 6/23/2026 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 6/24/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 6/26/2026 | Approved | RAFAEL CORTES |
| Drywall Nailing | 7/2/2026 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 7/7/2026 | Partial Approval | RAFAEL CORTES |