2130-2132 S WALNUT AVE 90291
Certificate Information: 2130-2132 S WALNUT AVE 90291
- Application / Permit
- 24010-10000-00582
- Plan Check / Job No.
- B24LA02681
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Construction of new single family dwelling with ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/14/2024
- Issuing Office
- Current Status
- CofO in Progress on 5/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/29/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 3/15/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/28/2024 | YOUNG KIM |
| Plan Check Approved | 9/17/2024 | ARSALAN SHABESTARI |
| Issued | 10/14/2024 | APPLICANT |
| CofO in Progress | 5/19/2026 | RUBEN RIVAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2024 | DIANA RENTERIA |
| Low Impact Development (LID) | Cleared | 6/11/2024 | AMMAR ELTAWIL |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 6/26/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 6/26/2024 | DIANA RENTERIA |
| Specific Plan | Cleared | 7/4/2024 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 7/6/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Lionel J; Lic. No.: NA4653 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/5/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/10/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/23/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/13/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | HERBERT GIRON |
| Sewer | 2/10/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/19/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/1/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/21/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/9/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Rough | 6/9/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 6/9/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 6/9/2025 | Approved | RUBEN RIVAS |
| Verify Sprinkler Sign Off | 6/9/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/23/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 7/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/6/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/6/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 8/6/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 8/18/2025 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 8/18/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/18/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/18/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/18/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/27/2025 | Partial Approval | RUBEN RIVAS |
| Drywall Nailing | 9/3/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/3/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/24/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Service/Power Release | 1/22/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 1/26/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 2/18/2026 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 2/18/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 3/13/2026 | Approved | RUBEN RIVAS |
| Service/Power Release | 3/13/2026 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | RUBEN RIVAS |
| Final | 4/24/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 4/24/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 4/24/2026 | Approved | RUBEN RIVAS |
| Smoke Detectors | 4/24/2026 | Approved | RUBEN RIVAS |
| Final | 5/7/2026 | Corrections Issued | RUBEN RIVAS |
| Final | 5/18/2026 | OK to Issue CofO | RUBEN RIVAS |