606 1/2-3/4 N FAIRVIEW AVE 90033

Certificate Information: 606 1/2-3/4 N FAIRVIEW AVE 90033

Application / Permit
24010-10000-00548
Plan Check / Job No.
B24LA02539
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(ePLAN) (2) New detached 2-story accessory dwelling per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). 1 ADU per floor. All work per engineer details.
Permit Issued
Issued on 11/26/2024
Issuing Office
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 VICTOR CHEN
Corrections Issued 2/27/2024 VICTOR CHEN
Quality Review Completed 3/7/2024 HAMID REZAEI
Applicant returned to address corrections 9/24/2024 VICTOR CHEN
Applicant returned to address corrections 11/4/2024 VICTOR CHEN
Applicant returned to address corrections 11/18/2024 VICTOR CHEN
Plan Check Approved 11/21/2024 VICTOR CHEN
Issued 11/26/2024 APPLICANT
CofO in Progress 10/16/2025 ALIZAH MAYAGOITIA
No Progress 10/19/2025 DEROLD HAUFF
CofO in Progress 10/19/2025 DEROLD HAUFF
Permit Finaled 10/21/2025 DEROLD HAUFF
CofO Issued 10/21/2025 DEROLD HAUFF
Permit Finaled 10/21/2025 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 3/1/2024 DAVID URITA
ZI Cleared 3/1/2024 DAVID URITA
Address approval Cleared 3/5/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 3/11/2024 JUSTIN BICOL
Sewer availability Cleared 3/11/2024 JUSTIN BICOL
SB8 RUD Cleared 3/26/2024 RICHARD TRUONG
Tenant Habitability Plan Cleared 3/27/2024 ISMAEL HERNANDEZ
Low Impact Development (LID) Cleared 10/17/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 10/21/2024 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 11/3/2024 VICTOR CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/13/2025 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 3/13/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Methane Barrier 3/17/2025 Conditional Approval NICHOLAS LOPEZ
METHANE-Rough 3/18/2025 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Approval ALIZAH MAYAGOITIA
METHANE-Subgrade 3/28/2025 Approved ALIZAH MAYAGOITIA
Deputy Methane Barrier 4/1/2025 Conditional Approval JOSH MEISTER
Excavation/Setback/Form/Re-Bar 4/8/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval ALIZAH MAYAGOITIA
METHANE-Final 5/30/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 5/30/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/4/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 6/4/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 6/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 6/9/2025 Approved ALIZAH MAYAGOITIA
Deputy Methane Barrier 6/11/2025 Conditional Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/23/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/24/2025 Approved ANTHONY RAMOS
Green Building Rough 6/24/2025 Approved ANTHONY RAMOS
Insulation 6/24/2025 Approved ANTHONY RAMOS
MERV13>=Rough 6/24/2025 Approved ANTHONY RAMOS
Verify Sprinkler Sign Off 6/24/2025 Approved ANTHONY RAMOS
Drywall Nailing 7/1/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 7/1/2025 Not Ready for Inspection GEM DE OCAMPO
Interior/Exterior Lathing 7/14/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 8/8/2025 Approved ALIZAH MAYAGOITIA
Sewer 8/13/2025 Approved ALIZAH MAYAGOITIA
Underground Mechanical 8/13/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/11/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 9/11/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 10/15/2025 Approved ALIZAH MAYAGOITIA
Final 10/15/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/15/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 10/15/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 10/15/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 10/15/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 10/15/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 10/15/2025 Approved ALIZAH MAYAGOITIA
Smoke Detectors 10/15/2025 Approved ALIZAH MAYAGOITIA