1698 W CONSTELLATION DR 90732

Certificate Information: 1698 W CONSTELLATION DR 90732

Application / Permit
24010-10000-00530
Plan Check / Job No.
B24LA01337
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
[60&61] NEW 3-STORY DUPLEX WITH ATTACHED 4-CAR GARAGE "BLDG 2B" -BLDG SPRINKLRED THRU-OUT
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 4/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 MAHNAZ NOURHASHEMI
Corrections Issued 2/9/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 3/1/2024 TU HUA
Applicant returned to address corrections 5/2/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 8/22/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 1/2/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 3/11/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 3/26/2025 MAHNAZ NOURHASHEMI
Issued 3/27/2025 APPLICANT
CofO in Progress 4/16/2026 JOSEPH MCGARRY
Permit Finaled 4/20/2026 ANSON MAGLASANG
CofO Issued 4/20/2026 ANSON MAGLASANG
Permit Finaled 4/20/2026 ANSON MAGLASANG

Permit Application Clearance Information

Miscellaneous Cleared 9/10/2024 JASON CHAN
Miscellaneous Cleared 9/10/2024 JASON CHAN
Miscellaneous Cleared 9/10/2024 JASON CHAN
Miscellaneous Cleared 9/10/2024 JASON CHAN
Miscellaneous Cleared 9/10/2024 JASON CHAN
Miscellaneous Cleared 9/10/2024 JASON CHAN
Private street Cleared 9/10/2024 JASON CHAN
Tract Map conditions Cleared 9/10/2024 JASON CHAN
Tract Map conditions Cleared 9/10/2024 JASON CHAN
ZA Case Cleared 9/10/2024 JASON CHAN
ZA Case Cleared 9/10/2024 JASON CHAN
ZA Case Cleared 9/10/2024 JASON CHAN
Address approval Cleared 10/24/2024 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 11/14/2024 DALIA MOKAYED
Landscape for retaining wall Cleared 11/14/2024 DALIA MOKAYED
Miscellaneous Cleared 11/14/2024 DALIA MOKAYED
Specific Plan Cleared 11/14/2024 DALIA MOKAYED
Construction near power lines Cleared 2/3/2025 ENRIQUE ACOSTA
Construction within easement Cleared 2/3/2025 ENRIQUE ACOSTA
Building over 36-ft Cleared 2/27/2025 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 2/27/2025 ERIK BEASLEY
Sewer availability Cleared 2/27/2025 ERIK BEASLEY
GPI Written Notices Cleared 2/28/2025 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 2/28/2025 MAHNAZ NOURHASHEMI
Eng Process Fee Ord 176,300 Cleared 3/3/2025 ERIK BEASLEY
Low Impact Development (LID) Cleared 3/3/2025 AMMAR ELTAWIL
Hydrant and Access approval Cleared 3/13/2025 KURT CORRAL

Contact Information

Architect Ly,, Christine Huynh; Lic. No.: NA23762       ,
Contractor R C Homes Inc; Lic. No.: 991134-B       ,
Engineer Bittner,, Ryan; Lic. No.: NA68167       ,
Engineer Ortiz,, Roberto; Lic. No.: S5512 1744 W KATELLA AVE STE 107      ORANGE, CA 92867

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/17/2025 Partial Approval JOSEPH MCGARRY
Sewer 4/17/2025 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/13/2025 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 5/13/2025 Conditional Approval JOSEPH MCGARRY
Grounding or Bonding 5/13/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/13/2025 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 5/16/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/3/2025 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Conditional Approval JOSEPH MCGARRY
Pre-Inspection 7/30/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/8/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 8/8/2025 Approved JOSEPH MCGARRY
Green Building Rough 8/8/2025 Approved JOSEPH MCGARRY
HVAC-Rough 8/8/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/8/2025 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 8/8/2025 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 8/8/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/11/2025 Partial Approval JOSEPH MCGARRY
Insulation 8/13/2025 Conditional Approval JOSEPH MCGARRY
Special/Order Compliance 8/13/2025 Corrections Issued JOSEPH MCGARRY
Drywall Nailing 8/20/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/2/2025 Partial Approval JOSEPH MCGARRY
Service/Power Release 11/20/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/3/2026 Approved JOSEPH MCGARRY
Shower Pan 3/3/2026 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/16/2026 Approved JOSEPH MCGARRY
Shower Pan 3/16/2026 Approved JOSEPH MCGARRY
ELECTRICAL-Final 4/15/2026 Approved JOSEPH MCGARRY
Final 4/15/2026 OK to Issue CofO JOSEPH MCGARRY
Footing/Foundation/Slab 4/15/2026 Approved JOSEPH MCGARRY
Green Building Final 4/15/2026 Approved JOSEPH MCGARRY
HVAC-Final 4/15/2026 Approved JOSEPH MCGARRY
PLUMBING-Final 4/15/2026 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Required JOSEPH MCGARRY
Smoke Detectors 4/15/2026 Approved JOSEPH MCGARRY