1405 W KELLAM AVE 90026

Certificate Information: 1405 W KELLAM AVE 90026

Application / Permit
24010-10000-00502
Plan Check / Job No.
B24LA02423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ePlan: 1. NEW DETACHED GARAGE
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/29/2024 ARSALAN SHABESTARI
Corrections Issued 3/16/2024 ARSALAN SHABESTARI
Quality Review Completed 3/27/2024 YOUNG KIM
Applicant returned to address corrections 10/10/2024 ARSALAN SHABESTARI
Applicant returned to address corrections 5/28/2025 ARSALAN SHABESTARI
Applicant returned to address corrections 6/11/2025 ARSALAN SHABESTARI
Plan Check Approved 6/17/2025 ARSALAN SHABESTARI
Plan Check Approved 6/30/2025 ARSALAN SHABESTARI
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/5/2024 DAVID LOPEZ
CPC Cleared 4/8/2024 MAYELA VILLA
Permit Cleared 4/8/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/15/2024 DAVID LOPEZ
Sewer availability Cleared 4/15/2024 DAVID LOPEZ
City Hist. Cultural Monument Cleared 6/3/2024 LAMBERT GIESSINGER
HPOZ Cleared 6/3/2024 LAMBERT GIESSINGER
Historic monument Cleared 6/3/2024 LAMBERT GIESSINGER
ZI Cleared 6/18/2024 DORIAN AGUILAR
Construction near power lines Cleared 8/3/2024 RIDWAN HARDY
Construction within easement Cleared 8/3/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/19/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/25/2024 DAVID LOPEZ
GPI Written Notices Cleared 6/17/2025 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 6/17/2025 ARSALAN SHABESTARI

Contact Information

Architect Guerrero,, Matthew David; Lic. No.: NA40191       ,
Contractor Owner-Builder       ,
Engineer Galbreath,, Sean; Lic. No.: NA5653       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 8/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 8/4/2025 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/5/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/3/2025 Corrections Issued HAMIK HARTOUNIAN
METHANE-Barrier 9/3/2025 Approved HAMIK HARTOUNIAN
METHANE-Subgrade 9/3/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/9/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/3/2026 Partial Approval HAMIK HARTOUNIAN